Certificate ⁦12⁩ — December 2025

Qassim vocational qualification centre — construction

Kingdom of Saudi Arabia

Saudi Contractors Authority

General Directorate of Finance & Procurement — Contracts & Procurement Department

Certificate no.
12
Date
⁦2026-01-12⁩
Hijri
23 Rajab 1447 AH
Reference
PAY-2024-017-12

Interim payment certificate no. (⁦12⁩)

For the work of December 2025

Contract number
SCA/2024/017
Etimad reference
2402200225
Contract
Qassim vocational qualification centre — construction
Contractor
Al-Bunyan Al-Rasekh Contracting Co.
Contractor VAT number
310102487310003
Project
Qassim Vocational Qualification Centre
Contract period
⁦2024-07-01⁩ — ⁦2027-05-31⁩
Original contract value
298,000,000
Current contract value
298,000,000
Linked milestone
Structure complete · MS-G3 Build complete

Certificate summary (SAR)

1Total value of work completed to date93,210,000
2Less: previous certificates(84,360,000)
3Value of work in this certificate8,850,000
4Less: retention (⁦10%⁩)(885,000)
5Less: advance payment recovery (⁦10%⁩)(885,000)
6Less: delay and breach penalties0
7Total deductions(1,770,000)
8Net before VAT7,080,000
9Add: value added tax (15%)1,062,000
10Net amount payable to the contractor8,142,000

Amount in words: Eight million one hundred forty-two thousand Saudi riyals only

Retention held up to this certificate: SAR 9.3M — released after final acceptance.

Work by contract item

ItemItem valuePreviousThis periodTo dateComplete
Preliminaries & mobilisation20,860,00013,760,0001,293,00015,053,000⁦72%⁩
Earthworks & foundations53,640,00021,415,0002,074,00023,489,000⁦44%⁩
Concrete & structural works92,380,00028,752,0003,033,00031,785,000⁦34%⁩
Mechanical, electrical & plumbing71,520,00014,016,0001,643,00015,659,000⁦22%⁩
Finishes & external works44,700,0005,594,000698,0006,292,000⁦14%⁩
Testing & commissioning14,900,000823,000109,000932,000⁦6%⁩
Total298,000,00084,360,0008,850,00093,210,000⁦31%⁩

Amounts in Saudi riyals.

Signatures and approvals

Contractor’s representative

Eng. Hamad S. Al-Hajri

Al-Hajri⁦2026-01-12⁩

Supervising engineer

Eng. Ibrahim A. Al-Ghamdi

Al-Ghamdi⁦2026-01-14⁩

Project manager

Eng. Ahmed Y. Asiri

Asiri⁦2026-01-17⁩

Finance & contracts

Khalid N. Al-Mutairi

Al-Mutairi⁦2026-01-20⁩

Authority holder

Dr. Abdullah S. Al-Qahtani

Al-Qahtani⁦2026-01-23⁩
Issued electronically through Munjaz Integration-ready for Etimad

Approval chain

Fully approved and sent for payment

  1. Certificate submitted⁦2026-01-12⁩

    Eng. Hamad S. Al-Hajri

  2. Engineer verifies quantities⁦2026-01-14⁩

    Eng. Ibrahim A. Al-Ghamdi · Director, Engineering Supervision

    Took 2 days

  3. Project manager certifies⁦2026-01-17⁩

    Eng. Ahmed Y. Asiri · Director, Construction Projects

    Took 3 days

  4. Payment order prepared⁦2026-01-20⁩

    Khalid N. Al-Mutairi · Senior Finance & Procurement SpecialistPayment request creator

    Took 3 days

  5. Final approval⁦2026-01-23⁩

    Dr. Abdullah S. Al-Qahtani · Secretary-General

    Took 3 days

You are viewing as Dr. Noura M. Al-Otaibi

Linked milestone & deliverables

The certificate is paid against a contract milestone, tied to the project’s milestone and its deliverables

  1. Contract milestoneStructure completeLate · ⁦2026-02-06⁩
  2. Project milestoneMS-G3Build completeMilestone not approved yet

Deliverables & completion certificates

Every linked deliverable is accepted with a completion certificate.

Segregation of duties

The platform checks these rules on every certificate

  • The payment request’s creator does not approve itKhalid N. Al-Mutairi → Dr. Abdullah S. Al-Qahtani
  • Whoever verified quantities does not prepare the payment orderEng. Ibrahim A. Al-Ghamdi → Khalid N. Al-Mutairi
  • The project manager does not approve the paymentEng. Ahmed Y. Asiri → Dr. Abdullah S. Al-Qahtani

Certificate history

23 January 2026

  1. Payment: Dr. Abdullah S. Al-Qahtani signed “Final approval”

    2026-01-23 13:00

20 January 2026

  1. Approval: Khalid N. Al-Mutairi signed “Payment order prepared”

    2026-01-20 13:00

17 January 2026

  1. Approval: Eng. Ahmed Y. Asiri signed “Project manager certifies”

    2026-01-17 13:00

14 January 2026

  1. Approval: Eng. Ibrahim A. Al-Ghamdi signed “Engineer verifies quantities”

    2026-01-14 13:00

12 January 2026

  1. Approval: Contractor signed “Certificate submitted”

    2026-01-12 09:00
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close