SCA/2024/017
Terms, guarantees, milestones, variation orders and payment certificates.
From original to current value
Variations pending: 1 worth SAR 8.4M — if approved the value becomes SAR 306.4M
43% of the current value paid
Paid
128.1Mof a current value of SAR 298M
Value of each certificate
The last 14 — gross and net
Approved: 18
Count: 18 · in the approval chain: 0
| Certificate | Submitted | Gross | Retention | Deductions | VAT | Net | Status | |
|---|---|---|---|---|---|---|---|---|
| Certificate 18September 2026 | 2026-10-05 | 6.5M | 650K | 650K | 780K | 6M | Approved | |
| Certificate 17August 2026 | 2026-09-03 | 3.1M | 312K | 312K | 374.4K | 2.9M | Approved | |
| Certificate 16June 2026 | 2026-07-18 | 4.5M | 453K | 453K | 543.6K | 4.2M | Approved | |
| Certificate 15May 2026 | 2026-06-01 | 6.1M | 610K | 610K | 732K | 5.6M | Approved | |
| Certificate 14March 2026 | 2026-04-16 | 6.3M | 625K | 625K | 750K | 5.8M | Approved | |
| Certificate 13February 2026 | 2026-02-28 | 8.4M | 839K | 839K | 1M | 7.7M | Approved | |
| Certificate 12December 2025 | 2026-01-12 | 8.9M | 885K | 885K | 1.1M | 8.1M | Approved | |
| Certificate 11November 2025 | 2025-11-26 | 8.4M | 843K | 843K | 1M | 7.8M | Approved | |
| Certificate 10September 2025 | 2025-10-10 | 10.7M | 1.1M | 1.1M | 1.3M | 9.8M | Approved | |
| Certificate 9August 2025 | 2025-08-25 | 9.3M | 931K | 931K | 1.1M | 8.6M | Approved | |
| Certificate 8June 2025 | 2025-07-09 | 9.3M | 925K | 925K | 1.1M | 8.5M | Approved | |
| Certificate 7May 2025 | 2025-05-23 | 10.2M | 1M | 1M | 1.2M | 9.4M | Approved | |
| Certificate 6March 2025 | 2025-04-06 | 7.9M | 788K | 788K | 945.6K | 7.2M | Approved | |
| Certificate 5January 2025 | 2025-02-18 | 8.1M | 807K | 807K | 968.4K | 7.4M | Approved | |
| Certificate 4December 2024 | 2025-01-02 | 7.3M | 728K | 728K | 873.6K | 6.7M | Approved | |
| Certificate 3October 2024 | 2024-11-17 | 5.3M | 528K | 528K | 633.6K | 4.9M | Approved | |
| Certificate 2September 2024 | 2024-10-01 | 4.7M | 474K | 474K | 568.8K | 4.4M | Approved | |
| Certificate 1July 2024 | 2024-08-15 | 3.2M | 320K | 320K | 384K | 2.9M | Approved |