Saudi Contractors AuthorityMunjaz11My actionsNotifications

Certificate ⁦6⁩ — March 2025

Qassim vocational qualification centre — construction

Kingdom of Saudi Arabia

Saudi Contractors Authority

General Directorate of Finance & Procurement — Contracts & Procurement Department

Certificate no.
6
Date
⁦2025-04-06⁩
Hijri
8 Shawwal 1446 AH
Reference
PAY-2024-017-06

Interim payment certificate no. (⁦6⁩)

For the work of March 2025

Contract number
SCA/2024/017
Etimad reference
2402200225
Contract
Qassim vocational qualification centre — construction
Contractor
Al-Bunyan Al-Rasekh Contracting Co.
Contractor VAT number
310102487310003
Project
Qassim Vocational Qualification Centre
Contract period
⁦2024-07-01⁩ — ⁦2027-05-31⁩
Original contract value
298,000,000
Current contract value
298,000,000
Linked milestone
Earthworks & foundations complete · MS-G2 Designs approved

Certificate summary (SAR)

1Total value of work completed to date36,450,000
2Less: previous certificates(28,570,000)
3Value of work in this certificate7,880,000
4Less: retention (⁦10%⁩)(788,000)
5Less: advance payment recovery (⁦10%⁩)(788,000)
6Less: delay and breach penalties0
7Total deductions(1,576,000)
8Net before VAT6,304,000
9Add: value added tax (15%)945,600
10Net amount payable to the contractor7,249,600

Amount in words: Seven million two hundred forty-nine thousand six hundred Saudi riyals only

Retention held up to this certificate: SAR 3.6M — released after final acceptance.

Work by contract item

ItemItem valuePreviousThis periodTo dateComplete
Preliminaries & mobilisation20,860,0004,655,0001,232,0005,887,000⁦28%⁩
Earthworks & foundations53,640,0007,246,0001,939,0009,185,000⁦17%⁩
Concrete & structural works92,380,0009,737,0002,692,00012,429,000⁦13%⁩
Mechanical, electrical & plumbing71,520,0004,754,0001,370,0006,124,000⁦9%⁩
Finishes & external works44,700,0001,898,000562,0002,460,000⁦6%⁩
Testing & commissioning14,900,000280,00085,000365,000⁦2%⁩
Total298,000,00028,570,0007,880,00036,450,000⁦12%⁩

Amounts in Saudi riyals.

Signatures and approvals

Contractor’s representative

Eng. Hamad S. Al-Hajri

Al-Hajri⁦2025-04-06⁩

Supervising engineer

Eng. Ibrahim A. Al-Ghamdi

Al-Ghamdi⁦2025-04-08⁩

Project manager

Eng. Ahmed Y. Asiri

Asiri⁦2025-04-11⁩

Finance & contracts

Khalid N. Al-Mutairi

Al-Mutairi⁦2025-04-14⁩

Authority holder

Dr. Abdullah S. Al-Qahtani

Al-Qahtani⁦2025-04-17⁩
Issued electronically through Munjaz Integration-ready for Etimad

Approval chain

Fully approved and sent for payment

  1. Certificate submitted⁦2025-04-06⁩

    Eng. Hamad S. Al-Hajri

  2. Engineer verifies quantities⁦2025-04-08⁩

    Eng. Ibrahim A. Al-Ghamdi · Director, Engineering Supervision

    Took 2 days

  3. Project manager certifies⁦2025-04-11⁩

    Eng. Ahmed Y. Asiri · Director, Construction Projects

    Took 3 days

  4. Payment order prepared⁦2025-04-14⁩

    Khalid N. Al-Mutairi · Senior Finance & Procurement SpecialistPayment request creator

    Took 3 days

  5. Final approval⁦2025-04-17⁩

    Dr. Abdullah S. Al-Qahtani · Secretary-General

    Took 3 days

You are viewing as Dr. Noura M. Al-Otaibi

Linked milestone & deliverables

The certificate is paid against a contract milestone, tied to the project’s milestone and its deliverables

  1. Contract milestoneEarthworks & foundations completeDone · ⁦2025-04-25⁩
  2. Project milestoneMS-G2Designs approvedMilestone approved ⁦2026-02-03⁩1 evidence file

Deliverables & completion certificates

Every linked deliverable is accepted with a completion certificate.

Segregation of duties

The platform checks these rules on every certificate

  • The payment request’s creator does not approve itKhalid N. Al-Mutairi → Dr. Abdullah S. Al-Qahtani
  • Whoever verified quantities does not prepare the payment orderEng. Ibrahim A. Al-Ghamdi → Khalid N. Al-Mutairi
  • The project manager does not approve the paymentEng. Ahmed Y. Asiri → Dr. Abdullah S. Al-Qahtani

Certificate history

17 April 2025

  1. Payment: Dr. Abdullah S. Al-Qahtani signed “Final approval”

    2025-04-17 13:00

14 April 2025

  1. Approval: Khalid N. Al-Mutairi signed “Payment order prepared”

    2025-04-14 13:00

11 April 2025

  1. Approval: Eng. Ahmed Y. Asiri signed “Project manager certifies”

    2025-04-11 13:00

8 April 2025

  1. Approval: Eng. Ibrahim A. Al-Ghamdi signed “Engineer verifies quantities”

    2025-04-08 13:00

6 April 2025

  1. Approval: Contractor signed “Certificate submitted”

    2025-04-06 09:00
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close