PRJ-2026-020Off track4ExecutionConstruction

Qassim Vocational Qualification Centre

Remove from watchlist

A training and skills-test centre in Buraydah serving the Qassim region, with 30 halls and practical workshops.

Early warning: ⁦81%⁩ chance of slipping within ⁦60⁩ days

Budget (BAC)

SAR 345M

Actual cost

SAR 159.8M

⁦46%⁩ of budget

Progress

⁦44%⁩Awaiting acceptance ⁦12%⁩

Estimate at completion

SAR 363.2M

SAR +18.2M

SPI · CPI

0.80Schedule performance index · 0.800.95Cost performance index · 0.95

Forecast finish

⁦2027-08-03⁩

64 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure5 March 2027

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate3 April 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate2 June 2024Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate24 November 2024Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate5 March 2027Closure · Not startedClosure · Not started

Milestones

Contractual, executive, payment, regulatory and project milestones: planned, forecast and actual dates, delay, owner, evidence and approval.

Milestone runway

2Achieved
0On track
2At risk
1Late
Average delay184 days
Jan 25Apr 25Jul 25Oct 25Jan 26Apr 26Jul 26Oct 26Jan 27Apr 27Jul 27
Contractual
Build completePlanned: ⁦2026-03-23⁩Forecast / actual: ⁦2027-03-09⁩Delay: 351 daysG3 +351
Executive
Project plan approvedPlanned: ⁦2025-01-14⁩Forecast / actual: ⁦2025-05-14⁩Delay: 120 daysG1 +120
Payment
Final handoverPlanned: ⁦2027-05-31⁩Forecast / actual: ⁦2027-08-01⁩Delay: 62 daysG5 +62
Regulatory
Testing & acceptance completePlanned: ⁦2026-12-09⁩Forecast / actual: ⁦2027-06-04⁩Delay: 177 daysG4 +177
Project
Designs approvedPlanned: ⁦2025-07-06⁩Forecast / actual: ⁦2026-02-03⁩Delay: 212 daysG2 +212

The hollow diamond is the approved baseline date, the solid one the actual or forecast, the line between them the delay

Milestone register

⁦5⁩ results
Export CSV
Project plan approvedMS-G1Executive⁦2025-01-14⁩⁦2025-05-14⁩⁦+120⁩ daysEng. Ahmed Y. AsiriEng. Ahmed Y. AsiriDirector, Construction ProjectsP-020a.asiri@sca.saAchieved1Approved
Designs approvedMS-G2Project⁦2025-07-06⁩⁦2026-02-03⁩⁦+212⁩ daysEng. Ahmed Y. AsiriEng. Ahmed Y. AsiriDirector, Construction ProjectsP-020a.asiri@sca.saAchieved1Approved
Build completeMS-G3Contractual⁦2026-03-23⁩⁦2027-03-09⁩⁦+351⁩ daysEng. Ahmed Y. AsiriEng. Ahmed Y. AsiriDirector, Construction ProjectsP-020a.asiri@sca.saLate0Not requested
Testing & acceptance completeMS-G4Regulatory⁦2026-12-09⁩⁦2027-06-04⁩⁦+177⁩ daysEng. Ahmed Y. AsiriEng. Ahmed Y. AsiriDirector, Construction ProjectsP-020a.asiri@sca.saAt risk0Not requested
Final handoverMS-G5Payment⁦2027-05-31⁩⁦2027-08-01⁩⁦+62⁩ daysEng. Ahmed Y. AsiriEng. Ahmed Y. AsiriDirector, Construction ProjectsP-020a.asiri@sca.saAt risk0Not requested
⁦1⁩–⁦5⁩ of ⁦5⁩

Deliverables register

Each deliverable with its acceptance criteria, files, versions, reviewer and approver, through its states from draft to approved.

Progress counted from deliverables

Project progress = the sum of the weights of deliverables accepted with a completion certificate. Nothing counts before it is accepted and certified.

Weights sum to ⁦100%⁩

Counted

⁦44%⁩

Awaiting acceptance

⁦12%⁩

Not handed in

⁦44%⁩

Deliverable flow

Pick a stage to filter the register
⁦12⁩ results
Export CSV
Project plan & baseline020-D1⁦3%⁩CRT-020-01ApprovedEng. Ahmed Y. AsiriEng. Ahmed Y. AsiriDirector, Construction ProjectsP-020a.asiri@sca.saEng. Bandar M. Al-Shammari⁦2024-10-19⁩V1⁦3⁩ of ⁦3⁩
Monitoring & reporting020-D2⁦3%⁩CRT-020-02ApprovedEng. Bandar M. Al-ShammariEng. Bandar M. Al-ShammariDirector General, Facilities & PremisesP-013b.alshammari@sca.saEng. Bandar M. Al-Shammari⁦2025-01-14⁩V1⁦3⁩ of ⁦3⁩
Detailed design020-D3⁦6%⁩CRT-020-03ApprovedEng. Bandar M. Al-ShammariEng. Bandar M. Al-ShammariDirector General, Facilities & PremisesP-013b.alshammari@sca.saEng. Bandar M. Al-Shammari⁦2025-04-10⁩V1⁦3⁩ of ⁦3⁩
Permits & approvals020-D4⁦6%⁩CRT-020-04ApprovedEng. Turki A. Al-AnaziEng. Turki A. Al-AnaziHead, Qualification & Training SectorP-010t.alanazi@sca.saEng. Bandar M. Al-Shammari⁦2025-07-06⁩V1⁦3⁩ of ⁦3⁩
Site works & excavation020-D5⁦13%⁩CRT-020-05ApprovedEng. Turki A. Al-AnaziEng. Turki A. Al-AnaziHead, Qualification & Training SectorP-010t.alanazi@sca.saEng. Bandar M. Al-Shammari⁦2025-10-01⁩V1⁦3⁩ of ⁦3⁩
Structure020-D6⁦13%⁩CRT-020-06ApprovedEng. Ahmed Y. AsiriEng. Ahmed Y. AsiriDirector, Construction ProjectsP-020a.asiri@sca.saEng. Bandar M. Al-Shammari⁦2025-12-27⁩V1⁦3⁩ of ⁦3⁩
Finishes020-D7⁦12%⁩—SubmittedEng. Bandar M. Al-ShammariEng. Bandar M. Al-ShammariDirector General, Facilities & PremisesP-013b.alshammari@sca.saEng. Bandar M. Al-Shammari⁦2026-03-23⁩V1⁦1⁩ of ⁦3⁩
Supply020-D8⁦10%⁩—DraftEng. Ahmed Y. AsiriEng. Ahmed Y. AsiriDirector, Construction ProjectsP-020a.asiri@sca.saEng. Bandar M. Al-Shammari⁦2026-06-18⁩V0⁦0⁩ of ⁦3⁩
Installation020-D9⁦10%⁩—DraftEng. Bandar M. Al-ShammariEng. Bandar M. Al-ShammariDirector General, Facilities & PremisesP-013b.alshammari@sca.saEng. Bandar M. Al-Shammari⁦2026-09-13⁩V0⁦0⁩ of ⁦3⁩
Testing & commissioning020-D10⁦10%⁩—DraftEng. Turki A. Al-AnaziEng. Turki A. Al-AnaziHead, Qualification & Training SectorP-010t.alanazi@sca.saEng. Bandar M. Al-Shammari⁦2026-12-09⁩V0⁦0⁩ of ⁦3⁩
Provisional acceptance020-D11⁦7%⁩—DraftEng. Bandar M. Al-ShammariEng. Bandar M. Al-ShammariDirector General, Facilities & PremisesP-013b.alshammari@sca.saEng. Bandar M. Al-Shammari⁦2027-03-05⁩V0⁦0⁩ of ⁦3⁩
Final acceptance020-D12⁦7%⁩—DraftEng. Turki A. Al-AnaziEng. Turki A. Al-AnaziHead, Qualification & Training SectorP-010t.alanazi@sca.saEng. Bandar M. Al-Shammari⁦2027-05-31⁩V0⁦0⁩ of ⁦3⁩
Total · 12⁦100%⁩
⁦1⁩–⁦12⁩ of ⁦12⁩