Saudi Contractors AuthorityMunjaz11My actionsNotifications

Certificate ⁦9⁩ — August 2025

Qassim vocational qualification centre — construction

Kingdom of Saudi Arabia

Saudi Contractors Authority

General Directorate of Finance & Procurement — Contracts & Procurement Department

Certificate no.
9
Date
⁦2025-08-25⁩
Hijri
2 Rabiʻ I 1447 AH
Reference
PAY-2024-017-09

Interim payment certificate no. (⁦9⁩)

For the work of August 2025

Contract number
SCA/2024/017
Etimad reference
2402200225
Contract
Qassim vocational qualification centre — construction
Contractor
Al-Bunyan Al-Rasekh Contracting Co.
Contractor VAT number
310102487310003
Project
Qassim Vocational Qualification Centre
Contract period
⁦2024-07-01⁩ — ⁦2027-05-31⁩
Original contract value
298,000,000
Current contract value
298,000,000
Linked milestone
Structure complete · MS-G3 Build complete

Certificate summary (SAR)

1Total value of work completed to date65,250,000
2Less: previous certificates(55,940,000)
3Value of work in this certificate9,310,000
4Less: retention (⁦10%⁩)(931,000)
5Less: advance payment recovery (⁦10%⁩)(931,000)
6Less: delay and breach penalties0
7Total deductions(1,862,000)
8Net before VAT7,448,000
9Add: value added tax (15%)1,117,200
10Net amount payable to the contractor8,565,200

Amount in words: Eight million five hundred sixty-five thousand two hundred Saudi riyals only

Retention held up to this certificate: SAR 6.5M — released after final acceptance.

Work by contract item

ItemItem valuePreviousThis periodTo dateComplete
Preliminaries & mobilisation20,860,0009,127,0001,411,00010,538,000⁦51%⁩
Earthworks & foundations53,640,00014,203,0002,240,00016,443,000⁦31%⁩
Concrete & structural works92,380,00019,065,0003,185,00022,250,000⁦24%⁩
Mechanical, electrical & plumbing71,520,0009,292,0001,670,00010,962,000⁦15%⁩
Finishes & external works44,700,0003,708,000696,0004,404,000⁦10%⁩
Testing & commissioning14,900,000545,000108,000653,000⁦4%⁩
Total298,000,00055,940,0009,310,00065,250,000⁦22%⁩

Amounts in Saudi riyals.

Signatures and approvals

Contractor’s representative

Eng. Hamad S. Al-Hajri

Al-Hajri⁦2025-08-25⁩

Supervising engineer

Eng. Ibrahim A. Al-Ghamdi

Al-Ghamdi⁦2025-08-27⁩

Project manager

Eng. Ahmed Y. Asiri

Asiri⁦2025-08-30⁩

Finance & contracts

Khalid N. Al-Mutairi

Al-Mutairi⁦2025-09-02⁩

Authority holder

Dr. Abdullah S. Al-Qahtani

Al-Qahtani⁦2025-09-05⁩
Issued electronically through Munjaz Integration-ready for Etimad

Approval chain

Fully approved and sent for payment

  1. Certificate submitted⁦2025-08-25⁩

    Eng. Hamad S. Al-Hajri

  2. Engineer verifies quantities⁦2025-08-27⁩

    Eng. Ibrahim A. Al-Ghamdi · Director, Engineering Supervision

    Took 2 days

  3. Project manager certifies⁦2025-08-30⁩

    Eng. Ahmed Y. Asiri · Director, Construction Projects

    Took 3 days

  4. Payment order prepared⁦2025-09-02⁩

    Khalid N. Al-Mutairi · Senior Finance & Procurement SpecialistPayment request creator

    Took 3 days

  5. Final approval⁦2025-09-05⁩

    Dr. Abdullah S. Al-Qahtani · Secretary-General

    Took 3 days

You are viewing as Dr. Noura M. Al-Otaibi

Linked milestone & deliverables

The certificate is paid against a contract milestone, tied to the project’s milestone and its deliverables

  1. Contract milestoneStructure completeLate · ⁦2026-02-06⁩
  2. Project milestoneMS-G3Build completeMilestone not approved yet

Deliverables & completion certificates

Every linked deliverable is accepted with a completion certificate.

Segregation of duties

The platform checks these rules on every certificate

  • The payment request’s creator does not approve itKhalid N. Al-Mutairi → Dr. Abdullah S. Al-Qahtani
  • Whoever verified quantities does not prepare the payment orderEng. Ibrahim A. Al-Ghamdi → Khalid N. Al-Mutairi
  • The project manager does not approve the paymentEng. Ahmed Y. Asiri → Dr. Abdullah S. Al-Qahtani

Certificate history

5 September 2025

  1. Payment: Dr. Abdullah S. Al-Qahtani signed “Final approval”

    2025-09-05 13:00

2 September 2025

  1. Approval: Khalid N. Al-Mutairi signed “Payment order prepared”

    2025-09-02 13:00

30 August 2025

  1. Approval: Eng. Ahmed Y. Asiri signed “Project manager certifies”

    2025-08-30 13:00

27 August 2025

  1. Approval: Eng. Ibrahim A. Al-Ghamdi signed “Engineer verifies quantities”

    2025-08-27 13:00

25 August 2025

  1. Approval: Contractor signed “Certificate submitted”

    2025-08-25 09:00
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close