Certificate ⁦10⁩ — September 2025

Qassim vocational qualification centre — construction

Kingdom of Saudi Arabia

Saudi Contractors Authority

General Directorate of Finance & Procurement — Contracts & Procurement Department

Certificate no.
10
Date
⁦2025-10-10⁩
Hijri
18 Rabiʻ II 1447 AH
Reference
PAY-2024-017-10

Interim payment certificate no. (⁦10⁩)

For the work of September 2025

Contract number
SCA/2024/017
Etimad reference
2402200225
Contract
Qassim vocational qualification centre — construction
Contractor
Al-Bunyan Al-Rasekh Contracting Co.
Contractor VAT number
310102487310003
Project
Qassim Vocational Qualification Centre
Contract period
⁦2024-07-01⁩ — ⁦2027-05-31⁩
Original contract value
298,000,000
Current contract value
298,000,000
Linked milestone
Structure complete · MS-G3 Build complete

Certificate summary (SAR)

1Total value of work completed to date75,930,000
2Less: previous certificates(65,250,000)
3Value of work in this certificate10,680,000
4Less: retention (⁦10%⁩)(1,068,000)
5Less: advance payment recovery (⁦10%⁩)(1,068,000)
6Less: delay and breach penalties0
7Total deductions(2,136,000)
8Net before VAT8,544,000
9Add: value added tax (15%)1,281,600
10Net amount payable to the contractor9,825,600

Amount in words: Nine million eight hundred twenty-five thousand six hundred Saudi riyals only

Retention held up to this certificate: SAR 7.6M — released after final acceptance.

Work by contract item

ItemItem valuePreviousThis periodTo dateComplete
Preliminaries & mobilisation20,860,00010,666,0001,598,00012,264,000⁦59%⁩
Earthworks & foundations53,640,00016,589,0002,545,00019,134,000⁦36%⁩
Concrete & structural works92,380,00022,236,0003,656,00025,892,000⁦28%⁩
Mechanical, electrical & plumbing71,520,00010,816,0001,940,00012,756,000⁦18%⁩
Finishes & external works44,700,0004,311,000814,0005,125,000⁦11%⁩
Testing & commissioning14,900,000632,000127,000759,000⁦5%⁩
Total298,000,00065,250,00010,680,00075,930,000⁦25%⁩

Amounts in Saudi riyals.

Signatures and approvals

Contractor’s representative

Eng. Hamad S. Al-Hajri

Al-Hajri⁦2025-10-10⁩

Supervising engineer

Eng. Ibrahim A. Al-Ghamdi

Al-Ghamdi⁦2025-10-12⁩

Project manager

Eng. Ahmed Y. Asiri

Asiri⁦2025-10-15⁩

Finance & contracts

Khalid N. Al-Mutairi

Al-Mutairi⁦2025-10-18⁩

Authority holder

Dr. Abdullah S. Al-Qahtani

Al-Qahtani⁦2025-10-21⁩
Issued electronically through Munjaz Integration-ready for Etimad

Approval chain

Fully approved and sent for payment

  1. Certificate submitted⁦2025-10-10⁩

    Eng. Hamad S. Al-Hajri

  2. Engineer verifies quantities⁦2025-10-12⁩

    Eng. Ibrahim A. Al-Ghamdi · Director, Engineering Supervision

    Took 2 days

  3. Project manager certifies⁦2025-10-15⁩

    Eng. Ahmed Y. Asiri · Director, Construction Projects

    Took 3 days

  4. Payment order prepared⁦2025-10-18⁩

    Khalid N. Al-Mutairi · Senior Finance & Procurement SpecialistPayment request creator

    Took 3 days

  5. Final approval⁦2025-10-21⁩

    Dr. Abdullah S. Al-Qahtani · Secretary-General

    Took 3 days

You are viewing as Dr. Noura M. Al-Otaibi

Linked milestone & deliverables

The certificate is paid against a contract milestone, tied to the project’s milestone and its deliverables

  1. Contract milestoneStructure completeLate · ⁦2026-02-06⁩
  2. Project milestoneMS-G3Build completeMilestone not approved yet

Deliverables & completion certificates

Every linked deliverable is accepted with a completion certificate.

Segregation of duties

The platform checks these rules on every certificate

  • The payment request’s creator does not approve itKhalid N. Al-Mutairi → Dr. Abdullah S. Al-Qahtani
  • Whoever verified quantities does not prepare the payment orderEng. Ibrahim A. Al-Ghamdi → Khalid N. Al-Mutairi
  • The project manager does not approve the paymentEng. Ahmed Y. Asiri → Dr. Abdullah S. Al-Qahtani

Certificate history

21 October 2025

  1. Payment: Dr. Abdullah S. Al-Qahtani signed “Final approval”

    2025-10-21 13:00

18 October 2025

  1. Approval: Khalid N. Al-Mutairi signed “Payment order prepared”

    2025-10-18 13:00

15 October 2025

  1. Approval: Eng. Ahmed Y. Asiri signed “Project manager certifies”

    2025-10-15 13:00

12 October 2025

  1. Approval: Eng. Ibrahim A. Al-Ghamdi signed “Engineer verifies quantities”

    2025-10-12 13:00

10 October 2025

  1. Approval: Contractor signed “Certificate submitted”

    2025-10-10 09:00
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close