Saudi Contractors AuthorityMunjaz11My actionsNotifications

Certificate ⁦2⁩ — September 2024

Qassim vocational qualification centre — construction

Kingdom of Saudi Arabia

Saudi Contractors Authority

General Directorate of Finance & Procurement — Contracts & Procurement Department

Certificate no.
2
Date
⁦2024-10-01⁩
Hijri
28 Rabiʻ I 1446 AH
Reference
PAY-2024-017-02

Interim payment certificate no. (⁦2⁩)

For the work of September 2024

Contract number
SCA/2024/017
Etimad reference
2402200225
Contract
Qassim vocational qualification centre — construction
Contractor
Al-Bunyan Al-Rasekh Contracting Co.
Contractor VAT number
310102487310003
Project
Qassim Vocational Qualification Centre
Contract period
⁦2024-07-01⁩ — ⁦2027-05-31⁩
Original contract value
298,000,000
Current contract value
298,000,000
Linked milestone
Earthworks & foundations complete · MS-G2 Designs approved

Certificate summary (SAR)

1Total value of work completed to date7,940,000
2Less: previous certificates(3,200,000)
3Value of work in this certificate4,740,000
4Less: retention (⁦10%⁩)(474,000)
5Less: advance payment recovery (⁦10%⁩)(474,000)
6Less: delay and breach penalties0
7Total deductions(948,000)
8Net before VAT3,792,000
9Add: value added tax (15%)568,800
10Net amount payable to the contractor4,360,800

Amount in words: Four million three hundred sixty thousand eight hundred Saudi riyals only

Retention held up to this certificate: SAR 794K — released after final acceptance.

Work by contract item

ItemItem valuePreviousThis periodTo dateComplete
Preliminaries & mobilisation20,860,000522,000760,0001,282,000⁦6%⁩
Earthworks & foundations53,640,000812,0001,189,0002,001,000⁦4%⁩
Concrete & structural works92,380,0001,091,0001,617,0002,708,000⁦3%⁩
Mechanical, electrical & plumbing71,520,000532,000802,0001,334,000⁦2%⁩
Finishes & external works44,700,000212,000324,000536,000⁦1%⁩
Testing & commissioning14,900,00031,00048,00079,000⁦1%⁩
Total298,000,0003,200,0004,740,0007,940,000⁦3%⁩

Amounts in Saudi riyals.

Signatures and approvals

Contractor’s representative

Eng. Hamad S. Al-Hajri

Al-Hajri⁦2024-10-01⁩

Supervising engineer

Eng. Ibrahim A. Al-Ghamdi

Al-Ghamdi⁦2024-10-03⁩

Project manager

Eng. Ahmed Y. Asiri

Asiri⁦2024-10-06⁩

Finance & contracts

Khalid N. Al-Mutairi

Al-Mutairi⁦2024-10-09⁩

Authority holder

Dr. Abdullah S. Al-Qahtani

Al-Qahtani⁦2024-10-12⁩
Issued electronically through Munjaz Integration-ready for Etimad

Approval chain

Fully approved and sent for payment

  1. Certificate submitted⁦2024-10-01⁩

    Eng. Hamad S. Al-Hajri

  2. Engineer verifies quantities⁦2024-10-03⁩

    Eng. Ibrahim A. Al-Ghamdi · Director, Engineering Supervision

    Took 2 days

  3. Project manager certifies⁦2024-10-06⁩

    Eng. Ahmed Y. Asiri · Director, Construction Projects

    Took 3 days

  4. Payment order prepared⁦2024-10-09⁩

    Khalid N. Al-Mutairi · Senior Finance & Procurement SpecialistPayment request creator

    Took 3 days

  5. Final approval⁦2024-10-12⁩

    Dr. Abdullah S. Al-Qahtani · Secretary-General

    Took 3 days

You are viewing as Dr. Noura M. Al-Otaibi

Linked milestone & deliverables

The certificate is paid against a contract milestone, tied to the project’s milestone and its deliverables

  1. Contract milestoneEarthworks & foundations completeDone · ⁦2025-04-25⁩
  2. Project milestoneMS-G2Designs approvedMilestone approved ⁦2026-02-03⁩1 evidence file

Deliverables & completion certificates

Every linked deliverable is accepted with a completion certificate.

Segregation of duties

The platform checks these rules on every certificate

  • The payment request’s creator does not approve itKhalid N. Al-Mutairi → Dr. Abdullah S. Al-Qahtani
  • Whoever verified quantities does not prepare the payment orderEng. Ibrahim A. Al-Ghamdi → Khalid N. Al-Mutairi
  • The project manager does not approve the paymentEng. Ahmed Y. Asiri → Dr. Abdullah S. Al-Qahtani

Certificate history

12 October 2024

  1. Payment: Dr. Abdullah S. Al-Qahtani signed “Final approval”

    2024-10-12 13:00

9 October 2024

  1. Approval: Khalid N. Al-Mutairi signed “Payment order prepared”

    2024-10-09 13:00

6 October 2024

  1. Approval: Eng. Ahmed Y. Asiri signed “Project manager certifies”

    2024-10-06 13:00

3 October 2024

  1. Approval: Eng. Ibrahim A. Al-Ghamdi signed “Engineer verifies quantities”