Certificate ⁦4⁩ — December 2024

Qassim vocational qualification centre — construction

Kingdom of Saudi Arabia

Saudi Contractors Authority

General Directorate of Finance & Procurement — Contracts & Procurement Department

Certificate no.
4
Date
⁦2025-01-02⁩
Hijri
2 Rajab 1446 AH
Reference
PAY-2024-017-04

Interim payment certificate no. (⁦4⁩)

For the work of December 2024

Contract number
SCA/2024/017
Etimad reference
2402200225
Contract
Qassim vocational qualification centre — construction
Contractor
Al-Bunyan Al-Rasekh Contracting Co.
Contractor VAT number
310102487310003
Project
Qassim Vocational Qualification Centre
Contract period
⁦2024-07-01⁩ — ⁦2027-05-31⁩
Original contract value
298,000,000
Current contract value
298,000,000
Linked milestone
Earthworks & foundations complete · MS-G2 Designs approved

Certificate summary (SAR)

1Total value of work completed to date20,500,000
2Less: previous certificates(13,220,000)
3Value of work in this certificate7,280,000
4Less: retention (⁦10%⁩)(728,000)
5Less: advance payment recovery (⁦10%⁩)(728,000)
6Less: delay and breach penalties0
7Total deductions(1,456,000)
8Net before VAT5,824,000
9Add: value added tax (15%)873,600
10Net amount payable to the contractor6,697,600

Amount in words: Six million six hundred ninety-seven thousand six hundred Saudi riyals only

Retention held up to this certificate: SAR 2.1M — released after final acceptance.

Work by contract item

ItemItem valuePreviousThis periodTo dateComplete
Preliminaries & mobilisation20,860,0002,155,0001,155,0003,310,000⁦16%⁩
Earthworks & foundations53,640,0003,355,0001,811,0005,166,000⁦10%⁩
Concrete & structural works92,380,0004,506,0002,485,0006,991,000⁦8%⁩
Mechanical, electrical & plumbing71,520,0002,198,0001,246,0003,444,000⁦5%⁩
Finishes & external works44,700,000878,000506,0001,384,000⁦3%⁩
Testing & commissioning14,900,000128,00077,000205,000⁦1%⁩
Total298,000,00013,220,0007,280,00020,500,000⁦7%⁩

Amounts in Saudi riyals.

Signatures and approvals

Contractor’s representative

Eng. Hamad S. Al-Hajri

Al-Hajri⁦2025-01-02⁩

Supervising engineer

Eng. Ibrahim A. Al-Ghamdi

Al-Ghamdi⁦2025-01-04⁩

Project manager

Eng. Ahmed Y. Asiri

Asiri⁦2025-01-07⁩

Finance & contracts

Khalid N. Al-Mutairi

Al-Mutairi⁦2025-01-10⁩

Authority holder

Dr. Abdullah S. Al-Qahtani

Al-Qahtani⁦2025-01-13⁩
Issued electronically through Munjaz Integration-ready for Etimad

Approval chain

Fully approved and sent for payment

  1. Certificate submitted⁦2025-01-02⁩

    Eng. Hamad S. Al-Hajri

  2. Engineer verifies quantities⁦2025-01-04⁩

    Eng. Ibrahim A. Al-Ghamdi · Director, Engineering Supervision

    Took 2 days

  3. Project manager certifies⁦2025-01-07⁩

    Eng. Ahmed Y. Asiri · Director, Construction Projects

    Took 3 days

  4. Payment order prepared⁦2025-01-10⁩

    Khalid N. Al-Mutairi · Senior Finance & Procurement SpecialistPayment request creator

    Took 3 days

  5. Final approval⁦2025-01-13⁩

    Dr. Abdullah S. Al-Qahtani · Secretary-General

    Took 3 days

You are viewing as Dr. Noura M. Al-Otaibi

Linked milestone & deliverables

The certificate is paid against a contract milestone, tied to the project’s milestone and its deliverables

  1. Contract milestoneEarthworks & foundations completeDone · ⁦2025-04-25⁩
  2. Project milestoneMS-G2Designs approvedMilestone approved ⁦2026-02-03⁩1 evidence file

Deliverables & completion certificates

Every linked deliverable is accepted with a completion certificate.

Segregation of duties

The platform checks these rules on every certificate

  • The payment request’s creator does not approve itKhalid N. Al-Mutairi → Dr. Abdullah S. Al-Qahtani
  • Whoever verified quantities does not prepare the payment orderEng. Ibrahim A. Al-Ghamdi → Khalid N. Al-Mutairi
  • The project manager does not approve the paymentEng. Ahmed Y. Asiri → Dr. Abdullah S. Al-Qahtani

Certificate history

13 January 2025

  1. Payment: Dr. Abdullah S. Al-Qahtani signed “Final approval”

    2025-01-13 13:00

10 January 2025

  1. Approval: Khalid N. Al-Mutairi signed “Payment order prepared”

    2025-01-10 13:00

7 January 2025

  1. Approval: Eng. Ahmed Y. Asiri signed “Project manager certifies”

    2025-01-07 13:00

4 January 2025

  1. Approval: Eng. Ibrahim A. Al-Ghamdi signed “Engineer verifies quantities”

    2025-01-04 13:00

2 January 2025

  1. Approval: Contractor signed “Certificate submitted”

    2025-01-02 09:00