Kingdom of Saudi Arabia
Saudi Contractors Authority
General Directorate of Finance & Procurement — Contracts & Procurement Department
- Certificate no.
- 4
- Date
- 2025-03-17
- Hijri
- 17 Ramadan 1446 AH
- Reference
- PAY-2024-022-04
Interim payment certificate no. (4)
For the work of February 2025
- Contract number
- SCA/2024/022
- Etimad reference
- 2402550290
- Contract
- Khamis Mushait training centre — rehabilitation works
- Contractor
- United Buildings & Operations Co.
- Contractor VAT number
- 320510488360003
- Project
- Khamis Mushait Training Centre Rehabilitation
- Contract period
- 2024-11-03 — 2026-10-31
- Original contract value
- 56,000,000
- Current contract value
- 56,000,000
- Linked milestone
- Earthworks & foundations complete · MS-G2 Designs approved
Certificate summary (SAR)
| 1 | Total value of work completed to date | 7,230,000 |
| 2 | Less: previous certificates | (4,690,000) |
| 3 | Value of work in this certificate | 2,540,000 |
| 4 | Less: retention (10%) | (254,000) |
| 5 | Less: advance payment recovery (10%) | (254,000) |
| 6 | Less: delay and breach penalties | 0 |
| 7 | Total deductions | (508,000) |
| 8 | Net before VAT | 2,032,000 |
| 9 | Add: value added tax (15%) | 304,800 |
| 10 | Net amount payable to the contractor | 2,336,800 |
Amount in words: Two million three hundred thirty-six thousand eight hundred Saudi riyals only
Retention held up to this certificate: SAR 723K — released after final acceptance.
Work by contract item
| Item | Item value | Previous | This period | To date | Complete |
|---|---|---|---|---|---|
| Preliminaries & mobilisation | 3,920,000 | 771,000 | 397,000 | 1,168,000 | 30% |
| Earthworks & foundations | 10,080,000 | 1,198,000 | 624,000 | 1,822,000 | 18% |
| Concrete & structural works | 17,360,000 | 1,597,000 | 868,000 | 2,465,000 | 14% |
| Mechanical, electrical & plumbing | 13,440,000 | 772,000 | 443,000 | 1,215,000 | 9% |
| Finishes & external works | 8,400,000 | 306,000 | 182,000 | 488,000 | 6% |
| Testing & commissioning | 2,800,000 | 46,000 | 26,000 | 72,000 | 3% |
| Total | 56,000,000 | 4,690,000 | 2,540,000 | 7,230,000 | 13% |
Amounts in Saudi riyals.
Signatures and approvals
Contractor’s representative
Eng. Samer A. Al-Qahtani
Supervising engineer
Eng. Ibrahim A. Al-Ghamdi
Project manager
Eng. Waleed O. Al-Juhani
Finance & contracts
Khalid N. Al-Mutairi
Authority holder
Dr. Abdullah S. Al-Qahtani