Kingdom of Saudi Arabia
Saudi Contractors Authority
General Directorate of Finance & Procurement — Contracts & Procurement Department
- Certificate no.
- 17
- Date
- 2026-04-08
- Hijri
- 20 Shawwal 1447 AH
- Reference
- PAY-2024-022-17
Interim payment certificate no. (17)
For the work of March 2026
- Contract number
- SCA/2024/022
- Etimad reference
- 2402550290
- Contract
- Khamis Mushait training centre — rehabilitation works
- Contractor
- United Buildings & Operations Co.
- Contractor VAT number
- 320510488360003
- Project
- Khamis Mushait Training Centre Rehabilitation
- Contract period
- 2024-11-03 — 2026-10-31
- Original contract value
- 56,000,000
- Current contract value
- 56,000,000
- Linked milestone
- MEP systems installed · MS-G4 Testing & acceptance complete
Certificate summary (SAR)
| 1 | Total value of work completed to date | 47,540,000 |
| 2 | Less: previous certificates | (45,650,000) |
| 3 | Value of work in this certificate | 1,890,000 |
| 4 | Less: retention (10%) | (189,000) |
| 5 | Less: advance payment recovery (10%) | (189,000) |
| 6 | Less: delay and breach penalties | 0 |
| 7 | Total deductions | (378,000) |
| 8 | Net before VAT | 1,512,000 |
| 9 | Add: value added tax (15%) | 226,800 |
| 10 | Net amount payable to the contractor | 1,738,800 |
Amount in words: One million seven hundred thirty-eight thousand eight hundred Saudi riyals only
Retention held up to this certificate: SAR 4.8M — released after final acceptance.
Work by contract item
| Item | Item value | Previous | This period | To date | Complete |
|---|---|---|---|---|---|
| Preliminaries & mobilisation | 3,920,000 | 3,849,000 | 71,000 | 3,920,000 | 100% |
| Earthworks & foundations | 10,080,000 | 9,850,000 | 230,000 | 10,080,000 | 100% |
| Concrete & structural works | 17,360,000 | 16,720,000 | 640,000 | 17,360,000 | 100% |
| Mechanical, electrical & plumbing | 13,440,000 | 11,800,000 | 696,000 | 12,496,000 | 93% |
| Finishes & external works | 8,400,000 | 2,993,000 | 216,000 | 3,209,000 | 38% |
| Testing & commissioning | 2,800,000 | 438,000 | 37,000 | 475,000 | 17% |
| Total | 56,000,000 | 45,650,000 | 1,890,000 | 47,540,000 | 85% |
Amounts in Saudi riyals.
Signatures and approvals
Contractor’s representative
Eng. Samer A. Al-Qahtani
Supervising engineer
Eng. Ibrahim A. Al-Ghamdi
Project manager
Eng. Waleed O. Al-Juhani
Finance & contracts
Khalid N. Al-Mutairi
Authority holder
Dr. Abdullah S. Al-Qahtani