Saudi Contractors AuthorityMunjaz11My actionsNotifications

Certificate ⁦9⁩ — July 2025

Khamis Mushait training centre — rehabilitation works

Kingdom of Saudi Arabia

Saudi Contractors Authority

General Directorate of Finance & Procurement — Contracts & Procurement Department

Certificate no.
9
Date
⁦2025-08-13⁩
Hijri
19 Safar 1447 AH
Reference
PAY-2024-022-09

Interim payment certificate no. (⁦9⁩)

For the work of July 2025

Contract number
SCA/2024/022
Etimad reference
2402550290
Contract
Khamis Mushait training centre — rehabilitation works
Contractor
United Buildings & Operations Co.
Contractor VAT number
320510488360003
Project
Khamis Mushait Training Centre Rehabilitation
Contract period
⁦2024-11-03⁩ — ⁦2026-10-31⁩
Original contract value
56,000,000
Current contract value
56,000,000
Linked milestone
Structure complete · MS-G3 Build complete

Certificate summary (SAR)

1Total value of work completed to date23,220,000
2Less: previous certificates(19,800,000)
3Value of work in this certificate3,420,000
4Less: retention (⁦10%⁩)(342,000)
5Less: advance payment recovery (⁦10%⁩)(342,000)
6Less: delay and breach penalties0
7Total deductions(684,000)
8Net before VAT2,736,000
9Add: value added tax (15%)410,400
10Net amount payable to the contractor3,146,400

Amount in words: Three million one hundred forty-six thousand four hundred Saudi riyals only

Retention held up to this certificate: SAR 2.3M — released after final acceptance.

Work by contract item

ItemItem valuePreviousThis periodTo dateComplete
Preliminaries & mobilisation3,920,0003,275,000476,0003,751,000⁦96%⁩
Earthworks & foundations10,080,0005,077,000774,0005,851,000⁦58%⁩
Concrete & structural works17,360,0006,743,0001,175,0007,918,000⁦46%⁩
Mechanical, electrical & plumbing13,440,0003,238,000663,0003,901,000⁦29%⁩
Finishes & external works8,400,0001,280,000287,0001,567,000⁦19%⁩
Testing & commissioning2,800,000187,00045,000232,000⁦8%⁩
Total56,000,00019,800,0003,420,00023,220,000⁦41%⁩

Amounts in Saudi riyals.

Signatures and approvals

Contractor’s representative

Eng. Samer A. Al-Qahtani

Al-Qahtani⁦2025-08-13⁩

Supervising engineer

Eng. Ibrahim A. Al-Ghamdi

Al-Ghamdi⁦2025-08-15⁩

Project manager

Eng. Waleed O. Al-Juhani

Al-Juhani⁦2025-08-18⁩

Finance & contracts

Khalid N. Al-Mutairi

Al-Mutairi⁦2025-08-21⁩

Authority holder

Dr. Abdullah S. Al-Qahtani

Al-Qahtani⁦2025-08-24⁩
Issued electronically through Munjaz Integration-ready for Etimad

Approval chain

Fully approved and sent for payment

  1. Certificate submitted⁦2025-08-13⁩

    Eng. Samer A. Al-Qahtani

  2. Engineer verifies quantities⁦2025-08-15⁩

    Eng. Ibrahim A. Al-Ghamdi · Director, Engineering Supervision

    Took 2 days

  3. Project manager certifies⁦2025-08-18⁩

    Eng. Waleed O. Al-Juhani · Director, Facilities Operations & Maintenance

    Took 3 days

  4. Payment order prepared⁦2025-08-21⁩

    Khalid N. Al-Mutairi · Senior Finance & Procurement SpecialistPayment request creator

    Took 3 days

  5. Final approval⁦2025-08-24⁩

    Dr. Abdullah S. Al-Qahtani · Secretary-General

    Took 3 days

You are viewing as Dr. Noura M. Al-Otaibi

Linked milestone & deliverables

The certificate is paid against a contract milestone, tied to the project’s milestone and its deliverables

  1. Contract milestoneStructure completeDone · ⁦2025-12-08⁩
  2. Project milestoneMS-G3Build completeMilestone approved ⁦2026-02-11⁩1 evidence file

Deliverables & completion certificates

Every linked deliverable is accepted with a completion certificate.

Segregation of duties

The platform checks these rules on every certificate

  • The payment request’s creator does not approve itKhalid N. Al-Mutairi → Dr. Abdullah S. Al-Qahtani
  • Whoever verified quantities does not prepare the payment orderEng. Ibrahim A. Al-Ghamdi → Khalid N. Al-Mutairi
  • The project manager does not approve the paymentEng. Waleed O. Al-Juhani → Dr. Abdullah S. Al-Qahtani

Certificate history

24 August 2025

  1. Payment: Dr. Abdullah S. Al-Qahtani signed “Final approval”

    2025-08-24 13:00

21 August 2025

  1. Approval: Khalid N. Al-Mutairi signed “Payment order prepared”

    2025-08-21 13:00

18 August 2025

  1. Approval: Eng. Waleed O. Al-Juhani signed “Project manager certifies”

    2025-08-18 13:00

15 August 2025

  1. Approval: Eng. Ibrahim A. Al-Ghamdi signed “Engineer verifies quantities”

    2025-08-15 13:00

13 August 2025

  1. Approval: Contractor signed “Certificate submitted”

    2025-08-13 09:00
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close