Certificate ⁦14⁩ — December 2025

Khamis Mushait training centre — rehabilitation works

Kingdom of Saudi Arabia

Saudi Contractors Authority

General Directorate of Finance & Procurement — Contracts & Procurement Department

Certificate no.
14
Date
⁦2026-01-08⁩
Hijri
19 Rajab 1447 AH
Reference
PAY-2024-022-14

Interim payment certificate no. (⁦14⁩)

For the work of December 2025

Contract number
SCA/2024/022
Etimad reference
2402550290
Contract
Khamis Mushait training centre — rehabilitation works
Contractor
United Buildings & Operations Co.
Contractor VAT number
320510488360003
Project
Khamis Mushait Training Centre Rehabilitation
Contract period
⁦2024-11-03⁩ — ⁦2026-10-31⁩
Original contract value
56,000,000
Current contract value
56,000,000
Linked milestone
MEP systems installed · MS-G4 Testing & acceptance complete

Certificate summary (SAR)

1Total value of work completed to date40,280,000
2Less: previous certificates(37,540,000)
3Value of work in this certificate2,740,000
4Less: retention (⁦10%⁩)(274,000)
5Less: advance payment recovery (⁦10%⁩)(274,000)
6Less: delay and breach penalties0
7Total deductions(548,000)
8Net before VAT2,192,000
9Add: value added tax (15%)328,800
10Net amount payable to the contractor2,520,800

Amount in words: Two million five hundred twenty thousand eight hundred Saudi riyals only

Retention held up to this certificate: SAR 4M — released after final acceptance.

Work by contract item

ItemItem valuePreviousThis periodTo dateComplete
Preliminaries & mobilisation3,920,0003,749,000171,0003,920,000⁦100%⁩
Earthworks & foundations10,080,0009,580,000500,00010,080,000⁦100%⁩
Concrete & structural works17,360,00015,282,0001,109,00016,391,000⁦94%⁩
Mechanical, electrical & plumbing13,440,0006,146,000621,0006,767,000⁦50%⁩
Finishes & external works8,400,0002,429,000290,0002,719,000⁦32%⁩
Testing & commissioning2,800,000354,00049,000403,000⁦14%⁩
Total56,000,00037,540,0002,740,00040,280,000⁦72%⁩

Amounts in Saudi riyals.

Signatures and approvals

Contractor’s representative

Eng. Samer A. Al-Qahtani

Al-Qahtani⁦2026-01-08⁩

Supervising engineer

Eng. Ibrahim A. Al-Ghamdi

Al-Ghamdi⁦2026-01-10⁩

Project manager

Eng. Waleed O. Al-Juhani

Al-Juhani⁦2026-01-13⁩

Finance & contracts

Khalid N. Al-Mutairi

Al-Mutairi⁦2026-01-16⁩

Authority holder

Dr. Abdullah S. Al-Qahtani

Al-Qahtani⁦2026-01-19⁩
Issued electronically through Munjaz Integration-ready for Etimad

Approval chain

Fully approved and sent for payment

  1. Certificate submitted⁦2026-01-08⁩

    Eng. Samer A. Al-Qahtani

  2. Engineer verifies quantities⁦2026-01-10⁩

    Eng. Ibrahim A. Al-Ghamdi · Director, Engineering Supervision

    Took 2 days

  3. Project manager certifies⁦2026-01-13⁩

    Eng. Waleed O. Al-Juhani · Director, Facilities Operations & Maintenance

    Took 3 days

  4. Payment order prepared⁦2026-01-16⁩

    Khalid N. Al-Mutairi · Senior Finance & Procurement SpecialistPayment request creator

    Took 3 days

  5. Final approval⁦2026-01-19⁩

    Dr. Abdullah S. Al-Qahtani · Secretary-General

    Took 3 days

You are viewing as Dr. Noura M. Al-Otaibi

Linked milestone & deliverables

The certificate is paid against a contract milestone, tied to the project’s milestone and its deliverables

  1. Contract milestoneMEP systems installedDone · ⁦2026-05-24⁩
  2. Project milestoneMS-G4Testing & acceptance completeMilestone approved ⁦2026-08-24⁩1 evidence file

Deliverables & completion certificates

Every linked deliverable is accepted with a completion certificate.

Segregation of duties

The platform checks these rules on every certificate

  • The payment request’s creator does not approve itKhalid N. Al-Mutairi → Dr. Abdullah S. Al-Qahtani
  • Whoever verified quantities does not prepare the payment orderEng. Ibrahim A. Al-Ghamdi → Khalid N. Al-Mutairi
  • The project manager does not approve the paymentEng. Waleed O. Al-Juhani → Dr. Abdullah S. Al-Qahtani

Certificate history

19 January 2026

  1. Payment: Dr. Abdullah S. Al-Qahtani signed “Final approval”

    2026-01-19 13:00

16 January 2026

  1. Approval: Khalid N. Al-Mutairi signed “Payment order prepared”

    2026-01-16 13:00

13 January 2026

  1. Approval: Eng. Waleed O. Al-Juhani signed “Project manager certifies”

    2026-01-13 13:00

10 January 2026

  1. Approval: Eng. Ibrahim A. Al-Ghamdi signed “Engineer verifies quantities”

    2026-01-10 13:00

8 January 2026

  1. Approval: Contractor signed “Certificate submitted”

    2026-01-08 09:00
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close