Authority → Sector → General Directorate → Department
Dr. Noura M. Al-Otaibi
Director, Project Management Office
Viewing as
Switch role to see the platform as they do
Calendar
Identity
Appearance
Quick actions
Go to
Projects
PRJ-2026-001
PRJ-2026-002
PRJ-2026-004
PRJ-2026-006
SCA/2025/002
Terms, guarantees, milestones, variation orders and payment certificates.
From original to current value
The original value and each approved variation
82% of the current value paid
Paid
of a current value of SAR 61.5M
Open claims
1
of 1 claim
Extension days claimed
45 days
If granted, it ends on 2026-12-15
Amounts claimed
None
Extension granted
From earlier claims
Extensions of time, cost claims and disputes
CLM-0009Extension of timeSubmitted
45-day extension — customs clearance of the entry gates
Outside the supplier’s control, documented by customs letters