Kingdom of Saudi Arabia
Saudi Contractors Authority
General Directorate of Finance & Procurement — Contracts & Procurement Department
- Certificate no.
- 2
- Date
- 2025-07-09
- Hijri
- 14 Muharram 1447 AH
- Reference
- PAY-2025-004-02
Interim payment certificate no. (2)
For the work of June 2025
- Contract number
- SCA/2025/004
- Etimad reference
- 2503390446
- Contract
- Cybersecurity programme & SOC delivery
- Contractor
- Cyber Shield Co.
- Contractor VAT number
- 310108124570003
- Project
- SCA Cybersecurity Programme
- Contract period
- 2025-03-02 — 2026-12-15
- Original contract value
- 31,500,000
- Current contract value
- 31,500,000
- Linked milestone
- Design approved · MS-G1 Project plan approved
Certificate summary (SAR)
| 1 | Total value of work completed to date | 5,720,000 |
| 2 | Less: previous certificates | (2,030,000) |
| 3 | Value of work in this certificate | 3,690,000 |
| 4 | Less: retention (5%) | (184,500) |
| 5 | Less: advance payment recovery (10%) | (369,000) |
| 6 | Less: delay and breach penalties | 0 |
| 7 | Total deductions | (553,500) |
| 8 | Net before VAT | 3,136,500 |
| 9 | Add: value added tax (15%) | 470,475 |
| 10 | Net amount payable to the contractor | 3,606,975 |
Amount in words: Three million six hundred six thousand nine hundred seventy-five Saudi riyals only
Retention held up to this certificate: SAR 286K — released after final acceptance.
Work by contract item
| Item | Item value | Previous | This period | To date | Complete |
|---|---|---|---|---|---|
| Analysis & design | 4,725,000 | 487,000 | 772,000 | 1,259,000 | 27% |
| Licences & platform | 6,300,000 | 551,000 | 936,000 | 1,487,000 | 24% |
| Build & configuration | 9,450,000 | 592,000 | 1,124,000 | 1,716,000 | 18% |
| Systems integration | 4,725,000 | 225,000 | 461,000 | 686,000 | 15% |
| Testing & acceptance | 3,150,000 | 107,000 | 236,000 | 343,000 | 11% |
| Training & run | 3,150,000 | 68,000 | 161,000 | 229,000 | 7% |
| Total | 31,500,000 | 2,030,000 | 3,690,000 | 5,720,000 | 18% |
Amounts in Saudi riyals.
Signatures and approvals
Contractor’s representative
Eng. Haitham S. Al-Zahrani
Supervising engineer
Hussam T. Al-Qurashi
Project manager
Eng. Yasser M. Al-Zahrani
Finance & contracts
Khalid N. Al-Mutairi
Authority holder
Dr. Abdullah S. Al-Qahtani