Project proposal & feasibility — Muqawil Release 4

ConfidentialApprovedV2

The economic and technical case for Muqawil Release ⁦4⁩: three options, NPV, payback and a sensitivity analysis.

More
Showing version:

Confidential

Kingdom of Saudi Arabia

Saudi Contractors Authority

Project Management Office (PMO)

Code
DOC-0202
Version
V2
Date
2024-09-15

Project proposal & feasibility — Muqawil Release ⁦4⁩

Muqawil Platform — Release 4

⁦1⁩. Problem & opportunity

This case addresses the need for Muqawil Platform — Release ⁦4⁩ and compares three options on cost, value and risk.

Project
Muqawil Platform — Release ⁦4⁩ (⁦PRJ-2026-014⁩)
Project manager
Eng. Sultan F. Al-Ghamdi
Budget
SAR ⁦86.4M⁩
Progress
⁦58%⁩ actual against ⁦67%⁩ planned
Forecast finish
⁦2027-05-12⁩

⁦2⁩. Options

OptionCostNPVRecommendation
Do nothing—NegativeRejected
PartialSAR ⁦51.8M⁩LowFallback
Full solutionSAR ⁦86.4M⁩HighestRecommended

⁦3⁩. Sensitivity

NPV stays positive up to an ⁦18%⁩ cost overrun or a full year’s delay in benefits.

Prepared by

Faisal A. Al-Shehri

Project manager

Eng. Sultan F. Al-Ghamdi
Issued from Munjaz — valid only once approved electronically1 / 1