Project status report — October 2026

InternalSubmittedV1

October status report: ⁦58%⁩ complete against ⁦67%⁩ planned, SPI ⁦0.87⁩, risks and the decisions needed.

More

Internal

Kingdom of Saudi Arabia

Saudi Contractors Authority

Project Management Office (PMO)

Code
DOC-0204
Version
V1
Date
2026-10-27

Project status report — October ⁦2026⁩

Muqawil Platform — Release 4

⁦1⁩. Executive summary

This report gives the position of Muqawil Platform — Release ⁦4⁩ to date: ⁦58%⁩ complete against ⁦67%⁩ planned, SPI ⁦0.87⁩, CPI ⁦0.96⁩, and an estimate at completion of SAR ⁦90.0M⁩.

Project
Muqawil Platform — Release ⁦4⁩ (⁦PRJ-2026-014⁩)
Project manager
Eng. Sultan F. Al-Ghamdi
Budget
SAR ⁦86.4M⁩
Progress
⁦58%⁩ actual against ⁦67%⁩ planned
Forecast finish
⁦2027-05-12⁩

⁦2⁩. Key findings

  • All planned milestones of the period met except one deferred
  • Actual spend rose in line with the work done
  • Three high risks under treatment, each with a named owner

⁦3⁩. Recommendations & decisions needed

  • Approve the proposed treatment of the high risks
  • Track the open findings with the vendor weekly

Prepared by

Eng. Sultan F. Al-Ghamdi
Issued from Munjaz — valid only once approved electronically1 / 1