Restricted
Kingdom of Saudi Arabia
Saudi Contractors Authority
Project Management Office (PMO)
- Code
- DOC-0206
- Version
- V1
- Date
- 2025-05-04
Muqawil build & run contract
Muqawil Platform — Release 4
The parties
This contract is made between the Saudi Contractors Authority (first party) and the contractor named in the data sheet (second party), under the Government Tenders and Procurement Law and its regulations.
- Project
- Muqawil Platform — Release 4 (PRJ-2026-014)
- Project manager
- Eng. Sultan F. Al-Ghamdi
- Budget
- SAR 86.4M
- Progress
- 58% actual against 67% planned
- Forecast finish
- 2027-05-12
Key terms
- Delay penalty 0.5% a week, capped at 10% of the contract value
- A 5% performance bond valid until final handover
- 10% retention on every certificate
Addendum 1
This addendum amends the payment schedule and adds complementary works within 10% of the contract value.
Prepared by
Project manager
Restricted