Muqawil build & run contract

Muqawil Platform — Release 4

The parties

This contract is made between the Saudi Contractors Authority (first party) and the contractor named in the data sheet (second party), under the Government Tenders and Procurement Law and its regulations.

Project
Muqawil Platform — Release ⁦4⁩ (⁦PRJ-2026-014⁩)
Project manager
Eng. Sultan F. Al-Ghamdi
Budget
SAR ⁦86.4M⁩
Progress
⁦58%⁩ actual against ⁦67%⁩ planned
Forecast finish
⁦2027-05-12⁩

Key terms

  • Delay penalty ⁦0.5%⁩ a week, capped at ⁦10%⁩ of the contract value
  • A ⁦5%⁩ performance bond valid until final handover
  • ⁦10%⁩ retention on every certificate

Addendum ⁦1⁩

This addendum amends the payment schedule and adds complementary works within ⁦10%⁩ of the contract value.

Prepared by

Khalid N. Al-Mutairi

Project manager

Eng. Sultan F. Al-Ghamdi
Issued from Munjaz — valid only once approved electronically1 / 1