Project proposal & feasibility — Project Tracking Platform

ConfidentialApprovedV3

The Project Tracking Platform proposal and feasibility after the Project Approval Committee’s condition that registered-project data be classified before sharing.

More
Showing version:

Confidential

Kingdom of Saudi Arabia

Saudi Contractors Authority

Project Management Office (PMO)

Code
DOC-0216
Version
V3
Date
2026-10-20

Project proposal & feasibility — Project Tracking Platform

Project Tracking Platform — National Phase

⁦1⁩. Problem & opportunity

This case addresses the need for Project Tracking Platform — National Phase and compares three options on cost, value and risk.

Project
Project Tracking Platform — National Phase (⁦PRJ-2026-023⁩)
Project manager
Rahaf I. Al-Nefaie
Budget
SAR ⁦28.0M⁩
Progress
⁦1%⁩ actual against ⁦1%⁩ planned
Forecast finish
⁦2027-12-31⁩

⁦2⁩. Options

OptionCostNPVRecommendation
Do nothing—NegativeRejected
PartialSAR ⁦16.8M⁩LowFallback
Full solutionSAR ⁦28.0M⁩HighestRecommended

⁦3⁩. Sensitivity

NPV stays positive up to an ⁦18%⁩ cost overrun or a full year’s delay in benefits.

Prepared by

Rahaf I. Al-Nefaie
Issued from Munjaz — valid only once approved electronically1 / 1