Saudi Contractors AuthorityMunjaz11My actionsNotifications
PRJ-2026-023On track2InitiationAgile

Project Tracking Platform — National Phase

Add to watchlist

A platform where owners, contractors and the ministry follow the progress, milestones and delays of registered construction projects in every region.

Budget (BAC)

SAR 28M

Actual cost

SAR 280K

⁦1%⁩ of budget

Progress

⁦1%⁩Awaiting acceptance ⁦0%⁩

Estimate at completion

SAR 28M

SPI · CPI

1.00Schedule performance index · 1.001.00Cost performance index · 1.00

Forecast finish

⁦2027-12-31⁩

On baseline

InitiationStage ⁦2⁩ of ⁦5⁩

Next gate:Planning6 September 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate8 July 2026Initiation · Current stageInitiation · Current stage
  3. Gate into «Planning»DecisionNot held yetDate6 September 2026Planning · Not startedPlanning · Not started
  4. Gate into «Execution»DecisionNot held yetExecution · Not startedExecution · Not started
  5. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started

Project health across eight dimensions

A weighted index, not just percent complete; each dimension leads to the tab that explains it.

Index over the last six reports

+6

May to October 2026

No material change in the health dimensions over the period.

Copilot summary

Generated from the live project data

The project is close to plan: ⁦1%⁩ done against ⁦1%⁩ planned.

SPI ⁦1.00⁩, CPI ⁦1.00⁩.

The project’s link, progress and status

How the project ties to the strategy, its progress counted from accepted deliverables, and its status history.

Strategic link

The main objective and initiative, the secondary links, and the project’s contribution to its initiative.

Main strategic objective· Axis: A Cornerstone of Sector DevelopmentSO-2.3Transparency and open sector information

Main initiative

SI-2.3.1Sector information & project tracking

Contribution to the initiative⁦57%⁩

The project’s share of the initiative’s project budget (2 projects)

Secondary links

No secondary links

Annual work-plan line
WP-2026-023
Classification
External

Project progress from accepted deliverables

Project progress = the sum of the weights of deliverables accepted with a completion certificate; nothing counts before acceptance.

Counted

⁦1%⁩

Awaiting acceptance ⁦0%⁩

Not handed in ⁦99%⁩

1 deliverable accepted

  • Project plan & baseline⁦1%⁩

0 deliverables under inspection or acceptance

    Progress & earned value

    ⁦1⁩ of ⁦5⁩ milestones complete

    Earned-value curve

    Planned, earned and actual to the data date, cumulative, with the forecast cost tail

    • Planned value
    • Earned value
    • Actual cost
    • Estimate at completion
    • Budget at completion

    Budget & commitments

    Commitments are ⁦2%⁩ of budget

    280K/ 28M
    Actual spend
    280K
    Committed
    600K
    Approved budget
    28M
    Estimate at completion
    28M

    Next milestones

    • Contract signed⁦2026-11-22⁩On track
    • 50% of works complete⁦2027-05-10⁩On track
    • Provisional acceptance⁦2027-11-23⁩On track
    • Closure⁦2027-12-31⁩On track

    Waiting on someone

    ⁦2⁩ approvals and ⁦1⁩ open action on this project

    Approvals & requests

    From «My actions» for this project

    Actions

    ⁦1⁩ open

    • Track the conditions attached to the Project Tracking Platform gateRahaf I. Al-NefaieIn 29 days2026-11-2616 Jumada II 1448 AHMedium

    Change requests

    Cost and schedule impact

    • No change requests

    Risks & impediments

    0 open risks, exposure SAR 0

    Risk map

    Probability
    5Probability: Almost certain · Impact: NegligibleLow · Score ⁦5⁩Probability: Almost certain · Impact: MinorMedium · Score ⁦10⁩Probability: Almost certain · Impact: ModerateHigh · Score ⁦15⁩Probability: Almost certain · Impact: MajorCritical · Score ⁦20⁩Probability: Almost certain · Impact: SevereCritical · Score ⁦25⁩
    4Probability: Likely · Impact: NegligibleLow · Score ⁦4⁩Probability: Likely · Impact: MinorMedium · Score ⁦8⁩Probability: Likely · Impact: ModerateMedium · Score ⁦12⁩Probability: Likely · Impact: MajorHigh · Score ⁦16⁩Probability: Likely · Impact: SevereCritical · Score ⁦20⁩
    3Probability: Possible · Impact: NegligibleLow · Score ⁦3⁩Probability: Possible · Impact: MinorLow · Score ⁦6⁩Probability: Possible · Impact: ModerateMedium · Score ⁦9⁩Probability: Possible · Impact: MajorMedium · Score ⁦12⁩Probability: Possible · Impact: SevereHigh · Score ⁦15⁩
    2Probability: Unlikely · Impact: NegligibleLow · Score ⁦2⁩Probability: Unlikely · Impact: MinorLow · Score ⁦4⁩Probability: Unlikely · Impact: ModerateLow · Score ⁦6⁩Probability: Unlikely · Impact: MajorMedium · Score ⁦8⁩Probability: Unlikely · Impact: SevereMedium · Score ⁦10⁩
    1Probability: Rare · Impact: NegligibleLow · Score ⁦1⁩Probability: Rare · Impact: MinorLow · Score ⁦2⁩Probability: Rare · Impact: ModerateLow · Score ⁦3⁩Probability: Rare · Impact: MajorLow · Score ⁦4⁩Probability: Rare · Impact: SevereLow · Score ⁦5⁩
    12345

    Impact

    • Critical0
    • High0
    • Medium0
    • Low0

    Top risks

    • No open risks

    Open impediments

    ⁦0⁩ escalated

    • No open impediments

    Deliverables

    ⁦1⁩ of ⁦11⁩ approved

    • Project plan & baseline023-D1 · V1 · CRT-023-01⁦1%⁩Rahaf I. Al-Nefaie⁦2026-11-11⁩2026-11-111 Jumada II 1448 AHApproved
    • Monitoring & reporting023-D2 · V0⁦4%⁩Faisal A. Al-ShehriIn 56 days2026-12-2314 Rajab 1448 AHDraft
    • Business requirements023-D3 · V0⁦9%⁩Faisal A. Al-ShehriIn 97 days2027-02-0225 Shaʻban 1448 AHDraft
    • Solution design023-D4 · V0⁦9%⁩Eng. Majed S. Al-RasheedIn 139 days2027-03-168 Shawwal 1448 AHDraft
    • Release 1023-D5 · V0⁦14%⁩Eng. Majed S. Al-RasheedIn 180 days2027-04-2619 Dhuʻl-Qiʻdah 1448 AHDraft
    • Release 2023-D6 · V0⁦14%⁩Rahaf I. Al-NefaieIn 222 days2027-06-072 Muharram 1449 AHDraft
    • Integrations023-D7 · V0⁦14%⁩Faisal A. Al-ShehriIn 263 days2027-07-1814 Safar 1449 AHDraft
    • System testing023-D8 · V0⁦10%⁩Rahaf I. Al-NefaieIn 305 days2027-08-2927 Rabiʻ I 1449 AHDraft
    • User acceptance testing023-D9 · V0⁦10%⁩Faisal A. Al-ShehriIn 346 days2027-10-099 Jumada I 1449 AHDraft
    • Training & change023-D10 · V0⁦8%⁩Faisal A. Al-ShehriIn 388 days2027-11-2021 Jumada II 1449 AHDraft
    • Go-live & handover023-D11 · V0⁦7%⁩Eng. Majed S. Al-RasheedIn 429 days2027-12-313 Shaʻban 1449 AHDraft

    Team, contracts & documents

    Team

    2 members

    Rahaf I. Al-Nefaie · Director, Data & InnovationFaisal A. Al-Shehri · Director General, Digital Platforms & Digital Services Portfolio Manager
    • Rahaf I. Al-NefaieRahaf I. Al-NefaieDirector, Data & InnovationProject managerP-027r.alnefaie@sca.sa⁦35%⁩
    • Faisal A. Al-ShehriFaisal A. Al-ShehriDirector General, Digital Platforms & Digital Services Portfolio ManagerBusiness owner, Project Tracking PlatformP-003f.alshehri@sca.sa⁦15%⁩

    Contracts

    0 contracts

    • No external contracts — delivered in-house
    Esc

    Quick actions

    Go to

    Projects

    ↑↓to move↵to openEscto close