Programme · PG-02 · Digital Services & Platforms Portfolio

Sector Information & Project Tracking Programme

At risk

The contracting sector information centre and data governance, and the project tracking platform.

Approved budget
SAR 52M

incl. SAR 2.5M programme reserve

Actual spend
SAR 14.3M

⁦28%⁩ of budget

EAC
SAR 50.6M+2.3%

Estimate at completion

Progress
⁦32%⁩

Planned ⁦37%⁩

Schedule performance index
0.95

Cost performance index 0.98

Manager

Rahaf I. Al-Nefaie

Director, Data & Innovation

Sponsor

Eng. Majed S. Al-Rasheed

Head, Digital Transformation Sector

Projects

2 projects

2025-08-03 — 2027-12-31

On track 1At risk 1

Programme objectives

What the programme must achieve, and the strategic objectives it serves.

  1. 1

    Document 60% of sector master data in an approved data catalogue

  2. 2

    Publish 24 sector reports and indicators and track registered projects nationally by the end of 2027

  3. 3

    One trusted source for case and party data

Programme benefits

From baseline to target

  • Sector master data documented

    by ⁦2027⁩
    Baseline 15Current 41 %Target 60
  • AI use cases in production

    by ⁦2027⁩
    Baseline 1Current 6 casesTarget 8

Roadmap

One lane per project: start to forecast finish, with the progress earned and the baseline finish.

EarnedRemainingBaseline finishSlip
202520262027
2027-01-18
2027-12-31

Dependencies between projects

What waits on what. Red links are on the programme’s critical path.

Critical path

What each project needs from the one before

  • Critical

    The project tracking platform needs documented, clean contractor and project master data

Shared risks

Risks that hit more than one project, managed at programme level.

12

Late sector-data cataloguing delays linking the tracking platform to project owners

PRK-02-1·Mitigate·Rahaf I. Al-Nefaie

Affects

Open risks in the programme’s projects

1 risk

Open risks in the programme’s projects
  • Critical0
  • High0
  • Medium1
  • Low0
  • Risks 1
Probability
5
4
3
2
1
12345

Impact

Open risks in the programme’s projects
Probability \ Impact12345
50 · Low0 · Medium0 · High0 · Critical0 · Critical
40 · Low0 · Medium0 · Medium0 · High0 · Critical
30 · Low0 · Low1 · Medium0 · Medium0 · High
20 · Low0 · Low0 · Low0 · Medium0 · Medium
10 · Low0 · Low0 · Low0 · Low0 · Low

Programme KPIs · Stakeholders

Stakeholders

Power against interest; click a person to see their role.

Power

Keep satisfied0

Manage closely3

Monitor0

Keep informed1

Eng. Majed S. Al-RasheedManage closelyRahaf I. Al-NefaieManage closelyTariq S. Al-YamiKeep informedEng. Yasser M. Al-ZahraniManage closely

Interest

Programme decisions

What the committees decided on the programme’s projects, and what the programme raised to them.

Committees

Projects Steering Committee

Monthly · Quorum ⁦5⁩

Dr. Mohammed I. Al-Subaie · Head, Strategy & Institutional Excellence SectorEng. Turki A. Al-Anazi · Head, Qualification & Training SectorEng. Majed S. Al-Rasheed · Head, Digital Transformation Sector
Chair: Dr. Abdullah S. Al-QahtaniNext meeting 2026-11-03
Project Approval Committee

Fortnightly · Quorum ⁦4⁩

Faisal A. Al-Shehri · Director General, Digital Platforms & Digital Services Portfolio ManagerDr. Amal F. Al-Sudairi · Director General, Strategy & PerformanceTariq S. Al-Yami · Head, Performance & Risk
Chair: Dr. Noura M. Al-OtaibiNext meeting 2026-11-04

Programme projects

The programme’s performance is computed from these projects.

⁦2⁩ results
Export CSV
Manager
Contracting Sector Information Centre & Data GovernancePRJ-2026-016Rahaf I. Al-Nefaie4ExecutionAt risk⁦62%⁩21.5M22.6M⁦+5.3%⁩0.89Schedule performance index · 0.890.95Cost performance index · 0.95
Project Tracking Platform — National PhasePRJ-2026-023Rahaf I. Al-Nefaie2InitiationOn track⁦1%⁩28M28M⁦0.0%⁩1.00Schedule performance index · 1.001.00Cost performance index · 1.00
Total · 249.5M50.6M
⁦1⁩–⁦2⁩ of ⁦2⁩

Budget shares

Budget shares

SAR 49.5M

Budget

  • Contracting Sector Information Centre & Data GovernanceSAR 21.5M⁦43%⁩
  • Project Tracking Platform — National PhaseSAR 28M⁦57%⁩
Budget shares
CategoryValueShare
Contracting Sector Information Centre & Data GovernanceSAR 21.5M⁦43%⁩
Project Tracking Platform — National PhaseSAR 28M⁦57%⁩
TotalSAR 49.5M⁦100%⁩