Internal
Kingdom of Saudi Arabia
Saudi Contractors Authority
Project Management Office (PMO)
- Code
- DOC-0309
- Version
- V1
- Date
- 2025-08-14
Closure & handover form — HR Self-Service
HR Self-Service
1. Executive summary
This report gives the position of HR Self-Service to date: 100% complete against 100% planned, SPI 1.00, CPI 1.06, and an estimate at completion of SAR 10.8M.
- Project
- HR Self-Service (PRJ-2026-032)
- Project manager
- Dana S. Al-Saleh
- Budget
- SAR 11.4M
- Progress
- 100% actual against 100% planned
- Forecast finish
- 2025-09-21
2. Key findings
- All planned milestones of the period met except one deferred
- Actual spend rose in line with the work done
- Three high risks under treatment, each with a named owner
3. Recommendations & decisions needed
- Approve the proposed treatment of the high risks
- Track the open findings with the vendor weekly
Prepared by
Dr. Noura M. Al-Otaibi
Project manager
Dana S. Al-Saleh
Internal