Saudi Contractors AuthorityMunjaz11My actionsNotifications

Lessons learned — HR Self-Service

InternalApprovedV1

Lessons learned — HR Self-Service

More

Internal

Kingdom of Saudi Arabia

Saudi Contractors Authority

Project Management Office (PMO)

Code
DOC-0310
Version
V1
Date
2025-08-20

Lessons learned — HR Self-Service

HR Self-Service

⁦1⁩. Executive summary

This report gives the position of HR Self-Service to date: ⁦100%⁩ complete against ⁦100%⁩ planned, SPI ⁦1.00⁩, CPI ⁦1.06⁩, and an estimate at completion of SAR ⁦10.8M⁩.

Project
HR Self-Service (⁦PRJ-2026-032⁩)
Project manager
Dana S. Al-Saleh
Budget
SAR ⁦11.4M⁩
Progress
⁦100%⁩ actual against ⁦100%⁩ planned
Forecast finish
⁦2025-09-21⁩

⁦2⁩. Key findings

  • All planned milestones of the period met except one deferred
  • Actual spend rose in line with the work done
  • Three high risks under treatment, each with a named owner

⁦3⁩. Recommendations & decisions needed

  • Approve the proposed treatment of the high risks
  • Track the open findings with the vendor weekly

Prepared by

Karim Haddad

Project manager

Dana S. Al-Saleh
Issued from Munjaz — valid only once approved electronically1 / 1

Internal

Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close