Saudi Contractors AuthorityMunjaz11My actionsNotifications

Lessons learned

Lessons by category, surfaced when a similar project is created.

Published lessons
19

From ⁦17⁩ projects

Times cited
83

In later requests and projects

High impact
10

Cost days or millions

In review
2

Waiting for PMO validation

Where lessons recur

Lessons per category · times cited

Press a category to filter the register.

Suggested for a similar project

Pick a project; lessons rank by type, phase, portfolio and proven reuse.

A Infrastructure project in Planning

  1. 99Same project typeFits its phaseSame portfolioProven
  2. 70Same project typeFits its phase
  3. 70Same project typeFits its phase
  4. 70Same project typeFits its phase
  5. 70Same project typeFits its phase

The register

Each lesson: context, what happened, impact, recommendation.

⁦21⁩ of ⁦21⁩

Settle the land handover before award, not after

LL-029 · Procurement · High impact · Published

  1. 1ContextThe SCA headquarters in Riyadh.
  2. 2What happenedThe site was handed over piecemeal because ⁦14⁩ plots had not yet been released by the bodies that held them.
  3. 3ImpactA ⁦120-day⁩ extension claim and SAR ⁦6.8M⁩ compensation.

Recommendation

Make “land available” a mandatory approval-gate item.

Captured by
Eng. Ahmed Y. Asiri
Date
2025-06-1014 Dhuʻl-Hijjah 1446 AH
Applies to
Infrastructure · Construction

Where it was used (⁦7⁩)