Saudi Contractors AuthorityMunjaz11My actionsNotifications

Lessons learned

Lessons by category, surfaced when a similar project is created.

Published lessons
19

From ⁦17⁩ projects

Times cited
83

In later requests and projects

High impact
10

Cost days or millions

In review
2

Waiting for PMO validation

Where lessons recur

Lessons per category · times cited

Press a category to filter the register.

Suggested for a similar project

Pick a project; lessons rank by type, phase, portfolio and proven reuse.

A Infrastructure project in Planning

  1. 99Same project typeFits its phaseSame portfolioProven
  2. 70Same project typeFits its phase
  3. 70Same project typeFits its phase
  4. 70Same project typeFits its phase
  5. 70Same project typeFits its phase

The register

Each lesson: context, what happened, impact, recommendation.

⁦21⁩ of ⁦21⁩

A fallback test environment for national integrations

LL-049 · Integration · Medium impact · In PMO review

  1. 1ContextThe shared Nafath test environment was down for nine days.
  2. 2What happenedThe integration team stopped entirely — there was no local simulator.
  3. 3ImpactAbout ⁦60⁩ person-days lost.

Recommendation

Build a simulator of the national interfaces in the first integration sprint.

Captured by
Hussam T. Al-Qurashi
Date
2026-10-0928 Rabiʻ II 1448 AH
Applies to
Digital

Where it was used (⁦1⁩)

Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close