Saudi Contractors AuthorityMunjaz11My actionsNotifications

Lessons learned

Lessons by category, surfaced when a similar project is created.

Published lessons
19

From ⁦17⁩ projects

Times cited
83

In later requests and projects

High impact
10

Cost days or millions

In review
2

Waiting for PMO validation

Where lessons recur

Lessons per category · times cited

Press a category to filter the register.

Suggested for a similar project

Pick a project; lessons rank by type, phase, portfolio and proven reuse.

A Infrastructure project in Planning

  1. 99Same project typeFits its phaseSame portfolioProven
  2. 70Same project typeFits its phase
  3. 70Same project typeFits its phase
  4. 70Same project typeFits its phase
  5. 70Same project typeFits its phase

The register

Each lesson: context, what happened, impact, recommendation.

⁦21⁩ of ⁦21⁩

Check the contractor’s financial capacity at pre-qualification

LL-2026-004 · Procurement · High impact · Published

  1. 1ContextThe Al-Khobar branch rehabilitation and extension.
  2. 2What happenedThe contractor ran into financial distress in month nine and supplies slowed; an executive task force was formed.
  3. 3ImpactSPI fell to ⁦0.71⁩ and the project went critical.

Recommendation

Add liquidity and existing commitments to pre-qualification for every tender over SAR ⁦50M⁩.

Captured by
Eng. Waleed O. Al-Juhani
Date
2026-09-2110 Rabiʻ II 1448 AH
Applies to
Infrastructure · Construction

Where it was used (⁦3⁩)

Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close