Saudi Contractors AuthorityMunjaz11My actionsNotifications

Enterprise & high-risk report

Risk reportConfidential

Saudi Contractors Authority · Second half of October 2026

Shown by your permissionsProject Management Office: 36 projects — everything in your scope

Saudi Contractors AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Risk report

Enterprise & high-risk report

Saudi Contractors Authority

Period
Second half of October 2026
Generated
22 October 202611 Jumada I 1448 AH
Submitted to
The Secretary-General and the Executive Committee
Owner
Tariq S. Al-Yami

Prepared by the Enterprise PMO — automatically, on Munjaz

Munjaz · RPT-06 · page ⁦1⁩ of ⁦5⁩Confidential
Enterprise & high-risk reportSaudi Contractors Authority

Executive summary

Written by Copilot from system data — review before sending

18 high risks are open with SAR 403.4M of exposure; the decisions needed centre on contractor distress and the large change requests.

12 projects are more than a month behind baseline; the worst: SCA Academy Campus, Riyadh (152 days), Al-Khobar Branch — Rehabilitation & Extension (126 days), Jeddah Branch & Qualification Centre (95 days).

The scope holds 36 projects with a budget of SAR 5.15B: 18 on track and 6 red or critical. Weighted progress is 52% against 57% planned, spend SAR 2.41B, and EAC SAR 5.56B (SAR 407.7M over).

Key figures

Projects
36
Budget
SAR 5.2B
Spent
SAR 2.4B
EAC
SAR 5.6B
Progress
⁦52%⁩ / ⁦57%⁩
SPI
0.85
CPI
0.93
High risks
18

Project health mix

  • On track 18
  • At risk 10
  • Off track 4
  • Critical 2
  • On hold 2
Munjaz · RPT-06 · page ⁦2⁩ of ⁦5⁩Confidential
Enterprise & high-risk reportSaudi Contractors Authority

Risk map

Risk map
  • Critical6
  • High12
  • Medium24
  • Low3
  • Risks 45
Probability
5
4
3
2
1
12345

Impact

Risk map
Probability \ Impact12345
50 · Low0 · Medium0 · High3 · Critical1 · Critical
40 · Low0 · Medium4 · Medium9 · High2 · Critical
30 · Low0 · Low12 · Medium5 · Medium3 · High
20 · Low0 · Low3 · Low1 · Medium2 · Medium
10 · Low0 · Low0 · Low0 · Low0 · Low

Exposure by risk category

Exposure by risk category
Exposure by risk category
CategoryExposure
FinancialSAR 282.4M
ScheduleSAR 53.4M
TechnicalSAR 43.1M
RegulatorySAR 31.2M
ContractualSAR 28.5M
CostSAR 8.4M
StakeholderSAR 4M
ResourceSAR 3.9M
SecuritySAR 3.6M
Munjaz · RPT-06 · page ⁦3⁩ of ⁦5⁩Confidential
Enterprise & high-risk reportSaudi Contractors Authority

Projects with the most at stake

ProjectBudgetProgressSlipHealth
SCA Headquarters, RiyadhSAR 1.2B⁦42%⁩74 daysOff track
SCA Academy Campus, RiyadhSAR 640M⁦57%⁩152 daysCritical
Asir Vocational Qualification CentreSAR 520M⁦2%⁩—On track
Al-Khobar Branch — Rehabilitation & ExtensionSAR 412M⁦68%⁩126 daysCritical
Qassim Vocational Qualification CentreSAR 345M⁦44%⁩64 daysOff track
Jeddah Branch & Qualification CentreSAR 286M⁦39%⁩95 daysOff track
Arar Vocational Qualification CentreSAR 238M⁦33%⁩28 daysAt risk
Wadi Al-Dawasir Vocational Qualification CentreSAR 210M⁦2%⁩184 daysOn hold
Hail Vocational Qualification CentreSAR 158M⁦52%⁩12 daysAt risk
SCA Backup Data CentreSAR 148M⁦72%⁩38 daysAt risk
Secure Enterprise NetworkSAR 132M⁦55%⁩33 daysAt risk
Unified Operations Centre for Centres & PlatformsSAR 110M⁦0%⁩—On track

The largest ⁦12⁩ of ⁦36⁩ by budget — the full table is in the Excel file

Munjaz · RPT-06 · page ⁦4⁩ of ⁦5⁩Confidential
Enterprise & high-risk reportSaudi Contractors Authority

Highest-exposure risks

RiskScoreExposure
Main contractor cash-flow distress and unpaid subcontractorsAl-Khobar Branch — Rehabilitation & Extension25SAR 36M
Steel and concrete price rises driving price-adjustment claimsSCA Headquarters, Riyadh20SAR 48M
Contractor financial claims piling up over unapproved variationsSCA Academy Campus, Riyadh20SAR 41M
Late handover of the northern plot and utility diversions in zones 3 and 4SCA Headquarters, Riyadh20SAR 31M
Unforeseen ground conditions and groundwater at the foundations of axes 12 to 16Qassim Vocational Qualification Centre20SAR 27M
Late land handover and title deed from the owning entity in Wadi Al-DawasirWadi Al-Dawasir Vocational Qualification Centre20SAR 12M
Ground-improvement costs up after the geotechnical surveyJeddah Branch & Qualification Centre16SAR 22.5M

Decisions needed

  1. 1

    Pay subcontractors directly on the Al-Khobar branch rehabilitation & extension

    The PMO recommends paying directly out of certificate 22 and deducting it from the main contractor’s dues.

  2. 2

    Refer the SCA Academy campus contractor’s claims to arbitration

    Legal recommends referral, with an independent engineer assessing the extension request in parallel.

  3. 3

    Approve the updated corrective plan for Muqawil Release 4

    The Steering Committee recommends conditional approval with a monthly progress review.

  4. 4

    Release SAR 22M of the HQ & regional centres portfolio reserve to speed up the HQ land handover

    Facilities & Premises recommends two tranches tied to site handovers.

Munjaz · RPT-06 · page ⁦5⁩ of ⁦5⁩Confidential
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close