Saudi Contractors AuthorityMunjaz11My actionsNotifications

Executive Committee report to the board — Q3 2026

Executive Committee or Board reportConfidential

Saudi Contractors Authority · Q3 2026

Shown by your permissionsProject Management Office: 36 projects — everything in your scope

Saudi Contractors AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Executive Committee or Board report

Executive Committee report to the board — Q3 2026

Saudi Contractors Authority

Period
Q3 2026
Generated
15 October 20264 Jumada I 1448 AH
Submitted to
The Executive Committee and the SCA board
Owner
Dr. Mohammed I. Al-Subaie

Prepared by the Enterprise PMO — automatically, on Munjaz

Munjaz · RPT-09 · page ⁦1⁩ of ⁦5⁩Confidential
Executive Committee report to the board — Q3 2026Saudi Contractors Authority

Executive summary

Written by Copilot from system data — review before sending

The scope holds 36 projects with a budget of SAR 5.15B: 18 on track and 6 red or critical. Weighted progress is 52% against 57% planned, spend SAR 2.41B, and EAC SAR 5.56B (SAR 407.7M over).

12 projects are more than a month behind baseline; the worst: SCA Academy Campus, Riyadh (152 days), Al-Khobar Branch — Rehabilitation & Extension (126 days), Jeddah Branch & Qualification Centre (95 days).

18 high risks are open with SAR 403.4M of exposure; the decisions needed centre on contractor distress and the large change requests.

Key figures

Projects
36
Budget
SAR 5.2B
Spent
SAR 2.4B
EAC
SAR 5.6B
Progress
⁦52%⁩ / ⁦57%⁩
SPI
0.85
CPI
0.93
High risks
18

Project health mix

  • On track 18
  • At risk 10
  • Off track 4
  • Critical 2
  • On hold 2
Munjaz · RPT-09 · page ⁦2⁩ of ⁦5⁩Confidential
Executive Committee report to the board — Q3 2026Saudi Contractors Authority

Strategic objectives

ObjectiveAchievedTarget
SO-1.1Simplify regulatory relationships and make doing business easier⁦72%⁩⁦85%⁩
SO-1.2Raise quality standards across contracting⁦79%⁩⁦85%⁩
SO-2.1Build capability and innovation in the sector⁦76%⁩⁦85%⁩
SO-2.2A collaborative environment across the sector⁦70%⁩⁦80%⁩
SO-2.3Transparency and open sector information⁦66%⁩⁦80%⁩
SO-3.1SCA services and programmes in every region⁦74%⁩⁦85%⁩
SO-3.2Efficient, sustainable SCA facilities⁦69%⁩⁦80%⁩
SO-3.3A better contractor experience and service quality⁦77%⁩⁦80%⁩
SO-4.1Strong technical capabilities⁦88%⁩⁦90%⁩
SO-4.2A mature operating model and accountability⁦85%⁩⁦90%⁩
SO-4.3A sustainable financial base⁦83%⁩⁦90%⁩
SO-4.4Leadership and human capital⁦82%⁩⁦85%⁩
Munjaz · RPT-09 · page ⁦3⁩ of ⁦5⁩Confidential
Executive Committee report to the board — Q3 2026Saudi Contractors Authority

Projects with the most at stake

ProjectSectorBudgetProgressHealth
SCA Headquarters, RiyadhSupportSAR 1.2B⁦42%⁩Off track
SCA Academy Campus, RiyadhQualificationSAR 640M⁦57%⁩Critical
Asir Vocational Qualification CentreSupportSAR 520M⁦2%⁩On track
Al-Khobar Branch — Rehabilitation & ExtensionSupportSAR 412M⁦68%⁩Critical
Qassim Vocational Qualification CentreSupportSAR 345M⁦44%⁩Off track
Jeddah Branch & Qualification CentreQualificationSAR 286M⁦39%⁩Off track
Arar Vocational Qualification CentreQualificationSAR 238M⁦33%⁩At risk
Wadi Al-Dawasir Vocational Qualification CentreQualificationSAR 210M⁦2%⁩On hold
Hail Vocational Qualification CentreQualificationSAR 158M⁦52%⁩At risk
SCA Backup Data CentreDigitalSAR 148M⁦72%⁩At risk
Secure Enterprise NetworkDigitalSAR 132M⁦55%⁩At risk
Unified Operations Centre for Centres & PlatformsDigitalSAR 110M⁦0%⁩On track

The largest ⁦12⁩ of ⁦36⁩ by budget — the full table is in the Excel file

Munjaz · RPT-09 · page ⁦4⁩ of ⁦5⁩Confidential
Executive Committee report to the board — Q3 2026Saudi Contractors Authority

Highest-exposure risks

RiskScoreExposure
Main contractor cash-flow distress and unpaid subcontractorsAl-Khobar Branch — Rehabilitation & Extension25SAR 36M
Steel and concrete price rises driving price-adjustment claimsSCA Headquarters, Riyadh20SAR 48M
Contractor financial claims piling up over unapproved variationsSCA Academy Campus, Riyadh20SAR 41M
Late handover of the northern plot and utility diversions in zones 3 and 4SCA Headquarters, Riyadh20SAR 31M
Unforeseen ground conditions and groundwater at the foundations of axes 12 to 16Qassim Vocational Qualification Centre20SAR 27M
Late land handover and title deed from the owning entity in Wadi Al-DawasirWadi Al-Dawasir Vocational Qualification Centre20SAR 12M
Ground-improvement costs up after the geotechnical surveyJeddah Branch & Qualification Centre16SAR 22.5M

Decisions needed

  1. 1

    Pay subcontractors directly on the Al-Khobar branch rehabilitation & extension

    The PMO recommends paying directly out of certificate 22 and deducting it from the main contractor’s dues.

  2. 2

    Refer the SCA Academy campus contractor’s claims to arbitration

    Legal recommends referral, with an independent engineer assessing the extension request in parallel.

  3. 3

    Approve the updated corrective plan for Muqawil Release 4

    The Steering Committee recommends conditional approval with a monthly progress review.

  4. 4

    Release SAR 22M of the HQ & regional centres portfolio reserve to speed up the HQ land handover

    Facilities & Premises recommends two tranches tied to site handovers.

Munjaz · RPT-09 · page ⁦5⁩ of ⁦5⁩Confidential
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close