Projects Steering Committee
Steers the Authority’s strategic portfolios and programmes: approves baselines, corrective plans and gate decisions for strategic projects, and tracks benefits and what they mean for member contractors and the sector.
Authority
Up to SAR 50M per decision, schedule extensions up to 180 days
Authority up to SAR 50M
Quorum
Five of seven voting members, including the chair or vice-chair
Voting
Two-thirds of those present for baseline decisions, simple majority otherwise
Members
87 with a vote
Quorum / voters
5/7Seats needed for a valid session
Sessions in 2026
104 decisions recorded
Resolutions
40 late
Next session
2026-11-03 · 10:00 — Steering Committee — November (digital services portfolio)
- SC-2026/09In progressDEC-2026-045
Qassim qualification centre revised baseline approved (+SAR 8.4M, +55 days), with monthly reports on the foundations of axes 12–16.
Eng. Ahmed Y. AsiriEng. Ahmed Y. AsiriDirector, Construction ProjectsP-020a.asiri@sca.saIn 11 days2026-11-0828 Jumada I 1448 AH- ACT-0320Approve the geotechnical report for axes 12–16In progress40%
- SC-2026/11In progressDEC-2026-031
Muqawil Release 4 corrective plan approved on condition the integration engineers are replaced within two weeks and the updated plan comes back in November.
Eng. Sultan F. Al-GhamdiEng. Sultan F. Al-GhamdiProject Manager, Muqawil Platform — Release 4P-005s.alghamdi@sca.saIn 4 days2026-11-0121 Jumada I 1448 AH - SC-2026/12In progressDEC-2026-037
Academy campus contractor claims referred to the contract’s dispute board; the claims file is prepared before the meeting.
Eng. Shahad M. Al-MalkiEng. Shahad M. Al-MalkiDirector, Academy FacilitiesP-022s.almalki@sca.saIn 9 days2026-11-0626 Jumada I 1448 AH- ACT-0310Prepare the claims file for the dispute boardIn progress55%
- SC-2026/13Not startedDEC-2026-042
The Project Tracking Platform — National Phase clears the planning gate with three conditions to be met by 26 November.
Rahaf I. Al-NefaieRahaf I. Al-NefaieDirector, Data & InnovationP-027r.alnefaie@sca.saIn 29 days2026-11-2616 Jumada II 1448 AH