Certificate ⁦9⁩ — April 2025

Project management & supervision — SCA Academy campus

Kingdom of Saudi Arabia

Saudi Contractors Authority

General Directorate of Finance & Procurement — Contracts & Procurement Department

Certificate no.
9
Date
⁦2025-05-02⁩
Hijri
4 Dhuʻl-Qiʻdah 1446 AH
Reference
PAY-2024-008-09

Interim payment certificate no. (⁦9⁩)

For the work of April 2025

Contract number
SCA/2024/008
Etimad reference
2401570108
Contract
Project management & supervision — SCA Academy campus
Contractor
Ma’alem International Project Management
Contractor VAT number
340304288130003
Project
SCA Academy Campus, Riyadh
Contract period
⁦2024-03-03⁩ — ⁦2027-06-30⁩
Original contract value
19,500,000
Current contract value
19,500,000
Linked milestone
Mid-term review · MS-G3 Build complete

Certificate summary (SAR)

1Total value of work completed to date5,660,000
2Less: previous certificates(4,820,000)
3Value of work in this certificate840,000
4Less: retention (⁦5%⁩)(42,000)
5Less: advance payment recovery (⁦0%⁩)0
6Less: delay and breach penalties0
7Total deductions(42,000)
8Net before VAT798,000
9Add: value added tax (15%)119,700
10Net amount payable to the contractor917,700

Amount in words: Nine hundred seventeen thousand seven hundred Saudi riyals only

Retention held up to this certificate: SAR 283K — released after final acceptance.

Work by contract item

ItemItem valuePreviousThis periodTo dateComplete
Resident engineering staff12,090,0003,008,000524,0003,532,000⁦29%⁩
Visiting specialists3,510,000868,000151,0001,019,000⁦29%⁩
Laboratory & testing2,340,000518,00093,000611,000⁦26%⁩
Reporting & technical office1,560,000426,00072,000498,000⁦32%⁩
Total19,500,0004,820,000840,0005,660,000⁦29%⁩

Amounts in Saudi riyals.

Signatures and approvals

Contractor’s representative

Eng. James Harlow

Harlow⁦2025-05-02⁩

Supervising engineer

Haifa S. Al-Ruwaili

Al-Ruwaili⁦2025-05-04⁩

Project manager

Eng. Shahad M. Al-Malki

Al-Malki⁦2025-05-07⁩

Finance & contracts

Khalid N. Al-Mutairi

Al-Mutairi⁦2025-05-10⁩

Authority holder

Munirah A. Al-Khalidi

Al-Khalidi⁦2025-05-13⁩
Issued electronically through Munjaz Integration-ready for Etimad

Approval chain

Fully approved and sent for payment

  1. Certificate submitted⁦2025-05-02⁩

    Eng. James Harlow

  2. Engineer verifies quantities⁦2025-05-04⁩

    Haifa S. Al-Ruwaili · Senior Financial Analyst

    Took 2 days

  3. Project manager certifies⁦2025-05-07⁩

    Eng. Shahad M. Al-Malki · Director, Academy Facilities

    Took 3 days

  4. Payment order prepared⁦2025-05-10⁩

    Khalid N. Al-Mutairi · Senior Finance & Procurement SpecialistPayment request creator

    Took 3 days

  5. Final approval⁦2025-05-13⁩

    Munirah A. Al-Khalidi · Director General, Finance & Procurement

    Took 3 days

You are viewing as Dr. Noura M. Al-Otaibi

Linked milestone & deliverables

The certificate is paid against a contract milestone, tied to the project’s milestone and its deliverables

  1. Contract milestoneMid-term reviewDone · ⁦2025-10-31⁩
  2. Project milestoneMS-G3Build completeMilestone approved ⁦2026-10-26⁩1 evidence file

Deliverables & completion certificates

No deliverable is tied to this milestone — the evidence is the milestone’s approval and its files.

Segregation of duties

The platform checks these rules on every certificate

  • The payment request’s creator does not approve itKhalid N. Al-Mutairi → Munirah A. Al-Khalidi
  • Whoever verified quantities does not prepare the payment orderHaifa S. Al-Ruwaili → Khalid N. Al-Mutairi
  • The project manager does not approve the paymentEng. Shahad M. Al-Malki → Munirah A. Al-Khalidi

Certificate history

13 May 2025

  1. Payment: Munirah A. Al-Khalidi signed “Final approval”

    2025-05-13 13:00

10 May 2025

  1. Approval: Khalid N. Al-Mutairi signed “Payment order prepared”

    2025-05-10 13:00

7 May 2025

  1. Approval: Eng. Shahad M. Al-Malki signed “Project manager certifies”

    2025-05-07 13:00

4 May 2025

  1. Approval: Haifa S. Al-Ruwaili signed “Engineer verifies quantities”

    2025-05-04 13:00

2 May 2025

  1. Approval: Contractor signed “Certificate submitted”

    2025-05-02 09:00