SCA/2024/008
Terms, guarantees, milestones, variation orders and payment certificates.
From original to current value
The original value and each approved variation
68% of the current value paid
Paid
13.2Mof a current value of SAR 19.5M
Value of each certificate
The last 14 — gross and net
Approved: 20
Count: 20 · in the approval chain: 0
| Certificate | Submitted | Gross | Retention | Deductions | VAT | Net | Status | |
|---|---|---|---|---|---|---|---|---|
| Certificate 20September 2026 | 2026-10-06 | 270K | 13.5K | 0 | 38.5K | 295K | Approved | |
| Certificate 19July 2026 | 2026-08-20 | 380K | 19K | 0 | 54.2K | 415.2K | Approved | |
| Certificate 18June 2026 | 2026-07-03 | 530K | 26.5K | 0 | 75.5K | 579K | Approved | |
| Certificate 17April 2026 | 2026-05-17 | 540K | 27K | 0 | 77K | 590K | Approved | |
| Certificate 16March 2026 | 2026-03-30 | 670K | 33.5K | 0 | 95.5K | 732K | Approved | |
| Certificate 15January 2026 | 2026-02-11 | 800K | 40K | 0 | 114K | 874K | Approved | |
| Certificate 14December 2025 | 2025-12-25 | 720K | 36K | 0 | 102.6K | 786.6K | Approved | |
| Certificate 13October 2025 | 2025-11-08 | 910K | 45.5K | 0 | 129.7K | 994.2K | Approved | |
| Certificate 12September 2025 | 2025-09-21 | 900K | 45K | 0 | 128.3K | 983.3K | Approved | |
| Certificate 11July 2025 | 2025-08-05 | 820K | 41K | 0 | 116.9K | 895.9K | Approved | |
| Certificate 10May 2025 | 2025-06-18 | 1M | 50K | 0 | 142.5K | 1.1M | Approved | |
| Certificate 9April 2025 | 2025-05-02 | 840K | 42K | 0 | 119.7K | 917.7K | Approved | |
| Certificate 8February 2025 | 2025-03-15 | 820K | 41K | 0 | 116.9K | 895.9K | Approved | |
| Certificate 7January 2025 | 2025-01-27 | 880K | 44K | 0 | 125.4K | 961.4K | Approved | |
| Certificate 6November 2024 | 2024-12-10 | 680K | 34K | 0 | 96.9K | 742.9K | Approved | |
| Certificate 5October 2024 | 2024-10-24 | 680K | 34K | 0 | 96.9K | 742.9K | Approved | |
| Certificate 4August 2024 | 2024-09-06 | 610K | 30.5K | 0 | 86.9K | 666.4K | Approved | |
| Certificate 3July 2024 | 2024-07-21 | 450K | 22.5K | 0 | 64.1K | 491.6K | Approved | |
| Certificate 2May 2024 | 2024-06-03 | 410K | 20.5K | 0 | 58.4K | 447.9K | Approved | |
| Certificate 1March 2024 | 2024-04-17 | 290K | 14.5K | 0 | 41.3K | 316.8K | Approved |