SCA/2024/014
Terms, guarantees, milestones, variation orders and payment certificates.
From original to current value
The original value and each approved variation
45% of the current value paid
Paid
12.1Mof a current value of SAR 26.8M
Value of each certificate
The last 14 — gross and net
Approved: 20
Count: 20 · in the approval chain: 0
| Certificate | Submitted | Gross | Retention | Deductions | VAT | Net | Status | |
|---|---|---|---|---|---|---|---|---|
| Certificate 20September 2026 | 2026-10-06 | 260K | 13K | 0 | 37.1K | 284.1K | Approved | |
| Certificate 19August 2026 | 2026-08-21 | 350K | 17.5K | 0 | 49.9K | 382.4K | Approved | |
| Certificate 18June 2026 | 2026-07-06 | 480K | 24K | 0 | 68.4K | 524.4K | Approved | |
| Certificate 17May 2026 | 2026-05-21 | 500K | 25K | 0 | 71.3K | 546.3K | Approved | |
| Certificate 16March 2026 | 2026-04-05 | 620K | 31K | 0 | 88.4K | 677.4K | Approved | |
| Certificate 15January 2026 | 2026-02-18 | 730K | 36.5K | 0 | 104K | 797.5K | Approved | |
| Certificate 14December 2025 | 2026-01-03 | 660K | 33K | 0 | 94.1K | 721.1K | Approved | |
| Certificate 13October 2025 | 2025-11-18 | 830K | 41.5K | 0 | 118.3K | 906.8K | Approved | |
| Certificate 12September 2025 | 2025-10-03 | 830K | 41.5K | 0 | 118.3K | 906.8K | Approved | |
| Certificate 11July 2025 | 2025-08-18 | 750K | 37.5K | 0 | 106.9K | 819.4K | Approved | |
| Certificate 10June 2025 | 2025-07-04 | 910K | 45.5K | 0 | 129.7K | 994.2K | Approved | |
| Certificate 9April 2025 | 2025-05-19 | 770K | 38.5K | 0 | 109.7K | 841.2K | Approved | |
| Certificate 8March 2025 | 2025-04-03 | 750K | 37.5K | 0 | 106.9K | 819.4K | Approved | |
| Certificate 7January 2025 | 2025-02-16 | 810K | 40.5K | 0 | 115.4K | 884.9K | Approved | |
| Certificate 6December 2024 | 2025-01-01 | 620K | 31K | 0 | 88.4K | 677.4K | Approved | |
| Certificate 5October 2024 | 2024-11-16 | 630K | 31.5K | 0 | 89.8K | 688.3K | Approved | |
| Certificate 4September 2024 | 2024-10-01 | 560K | 28K | 0 | 79.8K | 611.8K | Approved | |
| Certificate 3July 2024 | 2024-08-16 | 410K | 20.5K | 0 | 58.4K | 447.9K | Approved | |
| Certificate 2June 2024 | 2024-07-01 | 370K | 18.5K | 0 | 52.7K | 404.2K | Approved | |
| Certificate 1April 2024 | 2024-05-16 | 260K | 13K | 0 | 37.1K | 284.1K | Approved |