Kingdom of Saudi Arabia
Saudi Contractors Authority
General Directorate of Finance & Procurement — Contracts & Procurement Department
- Certificate no.
- 9
- Date
- 2026-05-16
- Hijri
- 29 Dhuʻl-Qiʻdah 1447 AH
- Reference
- PAY-2025-006-09
Interim payment certificate no. (9)
For the work of April 2026
- Contract number
- SCA/2025/006
- Etimad reference
- 2503530472
- Contract
- Backup data centre — civil & MEP works
- Contractor
- Al-Ufuq General Contracting Co.
- Contractor VAT number
- 320500924170003
- Project
- SCA Backup Data Centre
- Contract period
- 2025-05-04 — 2026-11-30
- Original contract value
- 92,000,000
- Current contract value
- 95,100,000including variations of SAR 3.1M
- Linked milestone
- MEP systems installed · MS-G4 Testing & acceptance complete
Certificate summary (SAR)
| 1 | Total value of work completed to date | 58,300,000 |
| 2 | Less: previous certificates | (52,450,000) |
| 3 | Value of work in this certificate | 5,850,000 |
| 4 | Less: retention (10%) | (585,000) |
| 5 | Less: advance payment recovery (10%) | (585,000) |
| 6 | Less: delay and breach penalties | 0 |
| 7 | Total deductions | (1,170,000) |
| 8 | Net before VAT | 4,680,000 |
| 9 | Add: value added tax (15%) | 702,000 |
| 10 | Net amount payable to the contractor | 5,382,000 |
Amount in words: Five million three hundred eighty-two thousand Saudi riyals only
Retention held up to this certificate: SAR 5.8M — released after final acceptance.
Work by contract item
| Item | Item value | Previous | This period | To date | Complete |
|---|---|---|---|---|---|
| Preliminaries & mobilisation | 6,657,000 | 6,161,000 | 496,000 | 6,657,000 | 100% |
| Earthworks & foundations | 17,118,000 | 15,729,000 | 1,389,000 | 17,118,000 | 100% |
| Concrete & structural works | 29,481,000 | 18,166,000 | 2,047,000 | 20,213,000 | 69% |
| Mechanical, electrical & plumbing | 22,824,000 | 8,540,000 | 1,254,000 | 9,794,000 | 43% |
| Finishes & external works | 14,265,000 | 3,365,000 | 570,000 | 3,935,000 | 28% |
| Testing & commissioning | 4,755,000 | 489,000 | 94,000 | 583,000 | 12% |
| Total | 95,100,000 | 52,450,000 | 5,850,000 | 58,300,000 | 61% |
Amounts in Saudi riyals.
Signatures and approvals
Contractor’s representative
Eng. Khalil I. Al-Dosari
Supervising engineer
Eng. Ibrahim A. Al-Ghamdi
Project manager
Eng. Omar H. Bawazir
Finance & contracts
Khalid N. Al-Mutairi
Authority holder
Dr. Abdullah S. Al-Qahtani