SCA/2025/006
Terms, guarantees, milestones, variation orders and payment certificates.
From original to current value
The original value and each approved variation
75% of the current value paid
Paid
71.8Mof a current value of SAR 95.1M
Value of each certificate
The last 13 — gross and net
Approved: 12
Count: 13 · in the approval chain: 1
| Certificate | Submitted | Gross | Retention | Deductions | VAT | Net | Status | |
|---|---|---|---|---|---|---|---|---|
| Certificate 13September 2026 | 2026-10-11 | 4.9M | 490K | 490K | 588K | 4.5M | In review | |
| Certificate 12August 2026 | 2026-09-08 | 5.6M | 560K | 560K | 672K | 5.2M | Approved | |
| Certificate 11July 2026 | 2026-08-07 | 2.9M | 288K | 288K | 345.6K | 2.6M | Approved | |
| Certificate 10June 2026 | 2026-06-27 | 5M | 502K | 502K | 602.4K | 4.6M | Approved | |
| Certificate 9April 2026 | 2026-05-16 | 5.9M | 585K | 585K | 702K | 5.4M | Approved | |
| Certificate 8March 2026 | 2026-04-05 | 7M | 695K | 695K | 834K | 6.4M | Approved | |
| Certificate 7February 2026 | 2026-02-22 | 8.8M | 879K | 879K | 1.1M | 8.1M | Approved | |
| Certificate 6December 2025 | 2026-01-12 | 7.4M | 741K | 741K | 889.2K | 6.8M | Approved | |
| Certificate 5November 2025 | 2025-12-01 | 8.2M | 816K | 816K | 979.2K | 7.5M | Approved | |
| Certificate 4October 2025 | 2025-10-21 | 7.7M | 769K | 769K | 922.8K | 7.1M | Approved | |
| Certificate 3August 2025 | 2025-09-09 | 5.5M | 552K | 552K | 662.4K | 5.1M | Approved | |
| Certificate 2July 2025 | 2025-07-30 | 4.9M | 494K | 494K | 592.8K | 4.5M | Approved | |
| Certificate 1May 2025 | 2025-06-18 | 3M | 299K | 299K | 358.8K | 2.8M | Approved |