Certificate ⁦7⁩ — February 2026

Backup data centre — civil & MEP works

Kingdom of Saudi Arabia

Saudi Contractors Authority

General Directorate of Finance & Procurement — Contracts & Procurement Department

Certificate no.
7
Date
⁦2026-02-22⁩
Hijri
5 Ramadan 1447 AH
Reference
PAY-2025-006-07

Interim payment certificate no. (⁦7⁩)

For the work of February 2026

Contract number
SCA/2025/006
Etimad reference
2503530472
Contract
Backup data centre — civil & MEP works
Contractor
Al-Ufuq General Contracting Co.
Contractor VAT number
320500924170003
Project
SCA Backup Data Centre
Contract period
⁦2025-05-04⁩ — ⁦2026-11-30⁩
Original contract value
92,000,000
Current contract value
95,100,000including variations of SAR 3.1M
Linked milestone
Structure complete · MS-G3 Build complete

Certificate summary (SAR)

1Total value of work completed to date45,500,000
2Less: previous certificates(36,710,000)
3Value of work in this certificate8,790,000
4Less: retention (⁦10%⁩)(879,000)
5Less: advance payment recovery (⁦10%⁩)(879,000)
6Less: delay and breach penalties0
7Total deductions(1,758,000)
8Net before VAT7,032,000
9Add: value added tax (15%)1,054,800
10Net amount payable to the contractor8,086,800

Amount in words: Eight million eighty-six thousand eight hundred Saudi riyals only

Retention held up to this certificate: SAR 4.6M — released after final acceptance.

Work by contract item

ItemItem valuePreviousThis periodTo dateComplete
Preliminaries & mobilisation6,657,0005,591,0001,066,0006,657,000⁦100%⁩
Earthworks & foundations17,118,00010,105,0002,052,00012,157,000⁦71%⁩
Concrete & structural works29,481,00012,493,0003,023,00015,516,000⁦53%⁩
Mechanical, electrical & plumbing22,824,0005,890,0001,754,0007,644,000⁦33%⁩
Finishes & external works14,265,0002,299,000772,0003,071,000⁦22%⁩
Testing & commissioning4,755,000332,000123,000455,000⁦10%⁩
Total95,100,00036,710,0008,790,00045,500,000⁦48%⁩

Amounts in Saudi riyals.

Signatures and approvals

Contractor’s representative

Eng. Khalil I. Al-Dosari

Al-Dosari⁦2026-02-22⁩

Supervising engineer

Eng. Ibrahim A. Al-Ghamdi

Al-Ghamdi⁦2026-02-24⁩

Project manager

Eng. Omar H. Bawazir

Bawazir⁦2026-02-27⁩

Finance & contracts

Khalid N. Al-Mutairi

Al-Mutairi⁦2026-03-02⁩

Authority holder

Dr. Abdullah S. Al-Qahtani

Al-Qahtani⁦2026-03-05⁩
Issued electronically through Munjaz Integration-ready for Etimad

Approval chain

Fully approved and sent for payment

  1. Certificate submitted⁦2026-02-22⁩

    Eng. Khalil I. Al-Dosari

  2. Engineer verifies quantities⁦2026-02-24⁩

    Eng. Ibrahim A. Al-Ghamdi · Director, Engineering Supervision

    Took 2 days

  3. Project manager certifies⁦2026-02-27⁩

    Eng. Omar H. Bawazir · Director, IT Infrastructure

    Took 3 days

  4. Payment order prepared⁦2026-03-02⁩

    Khalid N. Al-Mutairi · Senior Finance & Procurement SpecialistPayment request creator

    Took 3 days

  5. Final approval⁦2026-03-05⁩

    Dr. Abdullah S. Al-Qahtani · Secretary-General

    Took 3 days

You are viewing as Dr. Noura M. Al-Otaibi

Linked milestone & deliverables

The certificate is paid against a contract milestone, tied to the project’s milestone and its deliverables

  1. Contract milestoneStructure completeDone · ⁦2026-03-16⁩
  2. Project milestoneMS-G3Build completeMilestone approved ⁦2026-10-26⁩1 evidence file

Deliverables & completion certificates

Every linked deliverable is accepted with a completion certificate.

Segregation of duties

The platform checks these rules on every certificate

  • The payment request’s creator does not approve itKhalid N. Al-Mutairi → Dr. Abdullah S. Al-Qahtani
  • Whoever verified quantities does not prepare the payment orderEng. Ibrahim A. Al-Ghamdi → Khalid N. Al-Mutairi
  • The project manager does not approve the paymentEng. Omar H. Bawazir → Dr. Abdullah S. Al-Qahtani

Certificate history

5 March 2026

  1. Payment: Dr. Abdullah S. Al-Qahtani signed “Final approval”

    2026-03-05 13:00

2 March 2026

  1. Approval: Khalid N. Al-Mutairi signed “Payment order prepared”

    2026-03-02 13:00

27 February 2026

  1. Approval: Eng. Omar H. Bawazir signed “Project manager certifies”

    2026-02-27 13:00

24 February 2026

  1. Approval: Eng. Ibrahim A. Al-Ghamdi signed “Engineer verifies quantities”

    2026-02-24 13:00

22 February 2026

  1. Approval: Contractor signed “Certificate submitted”

    2026-02-22 09:00