Saudi Contractors AuthorityMunjaz11My actionsNotifications

Certificate ⁦6⁩ — December 2025

Backup data centre — civil & MEP works

Kingdom of Saudi Arabia

Saudi Contractors Authority

General Directorate of Finance & Procurement — Contracts & Procurement Department

Certificate no.
6
Date
⁦2026-01-12⁩
Hijri
23 Rajab 1447 AH
Reference
PAY-2025-006-06

Interim payment certificate no. (⁦6⁩)

For the work of December 2025

Contract number
SCA/2025/006
Etimad reference
2503530472
Contract
Backup data centre — civil & MEP works
Contractor
Al-Ufuq General Contracting Co.
Contractor VAT number
320500924170003
Project
SCA Backup Data Centre
Contract period
⁦2025-05-04⁩ — ⁦2026-11-30⁩
Original contract value
92,000,000
Current contract value
95,100,000including variations of SAR 3.1M
Linked milestone
Structure complete · MS-G3 Build complete

Certificate summary (SAR)

1Total value of work completed to date36,710,000
2Less: previous certificates(29,300,000)
3Value of work in this certificate7,410,000
4Less: retention (⁦10%⁩)(741,000)
5Less: advance payment recovery (⁦10%⁩)(741,000)
6Less: delay and breach penalties0
7Total deductions(1,482,000)
8Net before VAT5,928,000
9Add: value added tax (15%)889,200
10Net amount payable to the contractor6,817,200

Amount in words: Six million eight hundred seventeen thousand two hundred Saudi riyals only

Retention held up to this certificate: SAR 3.7M — released after final acceptance.

Work by contract item

ItemItem valuePreviousThis periodTo dateComplete
Preliminaries & mobilisation6,657,0004,883,0001,046,0005,929,000⁦89%⁩
Earthworks & foundations17,118,0007,556,0001,695,0009,251,000⁦54%⁩
Concrete & structural works29,481,0009,974,0002,544,00012,518,000⁦42%⁩
Mechanical, electrical & plumbing22,824,0004,749,0001,418,0006,167,000⁦27%⁩
Finishes & external works14,265,0001,867,000611,0002,478,000⁦17%⁩
Testing & commissioning4,755,000271,00096,000367,000⁦8%⁩
Total95,100,00029,300,0007,410,00036,710,000⁦39%⁩

Amounts in Saudi riyals.

Signatures and approvals

Contractor’s representative

Eng. Khalil I. Al-Dosari

Al-Dosari⁦2026-01-12⁩

Supervising engineer

Eng. Ibrahim A. Al-Ghamdi

Al-Ghamdi⁦2026-01-14⁩

Project manager

Eng. Omar H. Bawazir

Bawazir⁦2026-01-17⁩

Finance & contracts

Khalid N. Al-Mutairi

Al-Mutairi⁦2026-01-20⁩

Authority holder

Dr. Abdullah S. Al-Qahtani

Al-Qahtani⁦2026-01-23⁩
Issued electronically through Munjaz Integration-ready for Etimad

Approval chain

Fully approved and sent for payment

  1. Certificate submitted⁦2026-01-12⁩

    Eng. Khalil I. Al-Dosari

  2. Engineer verifies quantities⁦2026-01-14⁩

    Eng. Ibrahim A. Al-Ghamdi · Director, Engineering Supervision

    Took 2 days

  3. Project manager certifies⁦2026-01-17⁩

    Eng. Omar H. Bawazir · Director, IT Infrastructure

    Took 3 days

  4. Payment order prepared⁦2026-01-20⁩

    Khalid N. Al-Mutairi · Senior Finance & Procurement SpecialistPayment request creator

    Took 3 days

  5. Final approval⁦2026-01-23⁩

    Dr. Abdullah S. Al-Qahtani · Secretary-General

    Took 3 days

You are viewing as Dr. Noura M. Al-Otaibi

Linked milestone & deliverables

The certificate is paid against a contract milestone, tied to the project’s milestone and its deliverables

  1. Contract milestoneStructure completeDone · ⁦2026-03-16⁩
  2. Project milestoneMS-G3Build completeMilestone approved ⁦2026-10-26⁩1 evidence file

Deliverables & completion certificates

Every linked deliverable is accepted with a completion certificate.

Segregation of duties

The platform checks these rules on every certificate

  • The payment request’s creator does not approve itKhalid N. Al-Mutairi → Dr. Abdullah S. Al-Qahtani
  • Whoever verified quantities does not prepare the payment orderEng. Ibrahim A. Al-Ghamdi → Khalid N. Al-Mutairi
  • The project manager does not approve the paymentEng. Omar H. Bawazir → Dr. Abdullah S. Al-Qahtani

Certificate history

23 January 2026

  1. Payment: Dr. Abdullah S. Al-Qahtani signed “Final approval”

    2026-01-23 13:00

20 January 2026

  1. Approval: Khalid N. Al-Mutairi signed “Payment order prepared”

    2026-01-20 13:00

17 January 2026

  1. Approval: Eng. Omar H. Bawazir signed “Project manager certifies”

    2026-01-17 13:00

14 January 2026

  1. Approval: Eng. Ibrahim A. Al-Ghamdi signed “Engineer verifies quantities”

    2026-01-14 13:00

12 January 2026

  1. Approval: Contractor signed “Certificate submitted”

    2026-01-12 09:00
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close