Certificate ⁦9⁩ — June 2026

Wifaq Platform Release 2 development

Kingdom of Saudi Arabia

Saudi Contractors Authority

General Directorate of Finance & Procurement — Contracts & Procurement Department

Certificate no.
9
Date
⁦2026-07-09⁩
Hijri
24 Muharram 1448 AH
Reference
PAY-2025-010-09

Interim payment certificate no. (⁦9⁩)

For the work of June 2026

Contract number
SCA/2025/010
Etimad reference
2503810524
Contract
Wifaq Platform Release 2 development
Contractor
Digital Platforms Solutions Co.
Contractor VAT number
310105738640003
Project
Wifaq Dispute Settlement Platform — Release 2
Contract period
⁦2025-06-01⁩ — ⁦2026-11-30⁩
Original contract value
14,800,000
Current contract value
14,800,000
Linked milestone
Go-live · MS-G4 Testing & acceptance complete

Certificate summary (SAR)

1Total value of work completed to date11,080,000
2Less: previous certificates(9,970,000)
3Value of work in this certificate1,110,000
4Less: retention (⁦5%⁩)(55,500)
5Less: advance payment recovery (⁦10%⁩)(111,000)
6Less: delay and breach penalties0
7Total deductions(166,500)
8Net before VAT943,500
9Add: value added tax (15%)141,525
10Net amount payable to the contractor1,085,025

Amount in words: One million eighty-five thousand twenty-five Saudi riyals only

Retention held up to this certificate: SAR 554K — released after final acceptance.

Work by contract item

ItemItem valuePreviousThis periodTo dateComplete
Analysis & design2,220,0002,082,000138,0002,220,000⁦100%⁩
Licences & platform2,960,0002,719,000241,0002,960,000⁦100%⁩
Build & configuration4,440,0003,079,000383,0003,462,000⁦78%⁩
Systems integration2,220,0001,157,000173,0001,330,000⁦60%⁩
Testing & acceptance1,480,000565,000100,000665,000⁦45%⁩
Training & run1,480,000368,00075,000443,000⁦30%⁩
Total14,800,0009,970,0001,110,00011,080,000⁦75%⁩

Amounts in Saudi riyals.

Signatures and approvals

Contractor’s representative

Rayan M. Al-Shehri

Al-Shehri⁦2026-07-09⁩

Supervising engineer

Hussam T. Al-Qurashi

Al-Qurashi⁦2026-07-11⁩

Project manager

Karim Haddad

Haddad⁦2026-07-14⁩

Finance & contracts

Khalid N. Al-Mutairi

Al-Mutairi⁦2026-07-17⁩

Authority holder

Dr. Abdullah S. Al-Qahtani

Al-Qahtani⁦2026-07-20⁩
Issued electronically through Munjaz Integration-ready for Etimad

Approval chain

Fully approved and sent for payment

  1. Certificate submitted⁦2026-07-09⁩

    Rayan M. Al-Shehri

  2. Engineer verifies quantities⁦2026-07-11⁩

    Hussam T. Al-Qurashi · Senior Software Engineer – Integration

    Took 2 days

  3. Project manager certifies⁦2026-07-14⁩

    Karim Haddad · Senior Digital Delivery Consultant — PMO

    Took 3 days

  4. Payment order prepared⁦2026-07-17⁩

    Khalid N. Al-Mutairi · Senior Finance & Procurement SpecialistPayment request creator

    Took 3 days

  5. Final approval⁦2026-07-20⁩

    Dr. Abdullah S. Al-Qahtani · Secretary-General

    Took 3 days

You are viewing as Dr. Noura M. Al-Otaibi

Linked milestone & deliverables

The certificate is paid against a contract milestone, tied to the project’s milestone and its deliverables

  1. Contract milestoneGo-liveDone · ⁦2026-08-24⁩
  2. Project milestoneMS-G4Testing & acceptance completeMilestone approved ⁦2026-10-26⁩1 evidence file

Deliverables & completion certificates

Every linked deliverable is accepted with a completion certificate.

Segregation of duties

The platform checks these rules on every certificate

  • The payment request’s creator does not approve itKhalid N. Al-Mutairi → Dr. Abdullah S. Al-Qahtani
  • Whoever verified quantities does not prepare the payment orderHussam T. Al-Qurashi → Khalid N. Al-Mutairi
  • The project manager does not approve the paymentKarim Haddad → Dr. Abdullah S. Al-Qahtani

Certificate history

20 July 2026

  1. Payment: Dr. Abdullah S. Al-Qahtani signed “Final approval”

    2026-07-20 13:00

17 July 2026

  1. Approval: Khalid N. Al-Mutairi signed “Payment order prepared”

    2026-07-17 13:00

14 July 2026

  1. Approval: Karim Haddad signed “Project manager certifies”

    2026-07-14 13:00

11 July 2026

  1. Approval: Hussam T. Al-Qurashi signed “Engineer verifies quantities”

    2026-07-11 13:00

9 July 2026

  1. Approval: Contractor signed “Certificate submitted”

    2026-07-09 09:00