SCA/2025/010
Terms, guarantees, milestones, variation orders and payment certificates.
From original to current value
The original value and each approved variation
85% of the current value paid
Paid
12.6Mof a current value of SAR 14.8M
Value of each certificate
The last 11 — gross and net
Approved: 11
Count: 11 · in the approval chain: 0
| Certificate | Submitted | Gross | Retention | Deductions | VAT | Net | Status | |
|---|---|---|---|---|---|---|---|---|
| Certificate 11September 2026 | 2026-10-06 | 560K | 28K | 56K | 71.4K | 547.4K | Approved | |
| Certificate 10August 2026 | 2026-08-22 | 960K | 48K | 96K | 122.4K | 938.4K | Approved | |
| Certificate 9June 2026 | 2026-07-09 | 1.1M | 55.5K | 111K | 141.5K | 1.1M | Approved | |
| Certificate 8May 2026 | 2026-05-25 | 1.3M | 66K | 132K | 168.3K | 1.3M | Approved | |
| Certificate 7March 2026 | 2026-04-10 | 1.7M | 83.5K | 167K | 212.9K | 1.6M | Approved | |
| Certificate 6February 2026 | 2026-02-25 | 1.4M | 70.5K | 141K | 179.8K | 1.4M | Approved | |
| Certificate 5December 2025 | 2026-01-11 | 1.6M | 77.5K | 155K | 197.6K | 1.5M | Approved | |
| Certificate 4November 2025 | 2025-11-27 | 1.5M | 73K | 146K | 186.2K | 1.4M | Approved | |
| Certificate 3September 2025 | 2025-10-13 | 1.1M | 52.5K | 105K | 133.9K | 1M | Approved | |
| Certificate 2August 2025 | 2025-08-30 | 940K | 47K | 94K | 119.9K | 918.9K | Approved | |
| Certificate 1June 2025 | 2025-07-16 | 570K | 28.5K | 57K | 72.7K | 557.2K | Approved |