Kingdom of Saudi Arabia
Saudi Contractors Authority
General Directorate of Finance & Procurement — Contracts & Procurement Department
- Certificate no.
- 2
- Date
- 2025-08-30
- Hijri
- 7 Rabiʻ I 1447 AH
- Reference
- PAY-2025-010-02
Interim payment certificate no. (2)
For the work of August 2025
- Contract number
- SCA/2025/010
- Etimad reference
- 2503810524
- Contract
- Wifaq Platform Release 2 development
- Contractor
- Digital Platforms Solutions Co.
- Contractor VAT number
- 310105738640003
- Project
- Wifaq Dispute Settlement Platform — Release 2
- Contract period
- 2025-06-01 — 2026-11-30
- Original contract value
- 14,800,000
- Current contract value
- 14,800,000
- Linked milestone
- Design approved · MS-G1 Project plan approved
Certificate summary (SAR)
| 1 | Total value of work completed to date | 1,510,000 |
| 2 | Less: previous certificates | (570,000) |
| 3 | Value of work in this certificate | 940,000 |
| 4 | Less: retention (5%) | (47,000) |
| 5 | Less: advance payment recovery (10%) | (94,000) |
| 6 | Less: delay and breach penalties | 0 |
| 7 | Total deductions | (141,000) |
| 8 | Net before VAT | 799,000 |
| 9 | Add: value added tax (15%) | 119,850 |
| 10 | Net amount payable to the contractor | 918,850 |
Amount in words: Nine hundred eighteen thousand eight hundred fifty Saudi riyals only
Retention held up to this certificate: SAR 75.5K — released after final acceptance.
Work by contract item
| Item | Item value | Previous | This period | To date | Complete |
|---|---|---|---|---|---|
| Analysis & design | 2,220,000 | 131,000 | 201,000 | 332,000 | 15% |
| Licences & platform | 2,960,000 | 151,000 | 242,000 | 393,000 | 13% |
| Build & configuration | 4,440,000 | 169,000 | 284,000 | 453,000 | 10% |
| Systems integration | 2,220,000 | 66,000 | 115,000 | 181,000 | 8% |
| Testing & acceptance | 1,480,000 | 32,000 | 59,000 | 91,000 | 6% |
| Training & run | 1,480,000 | 21,000 | 39,000 | 60,000 | 4% |
| Total | 14,800,000 | 570,000 | 940,000 | 1,510,000 | 10% |
Amounts in Saudi riyals.
Signatures and approvals
Contractor’s representative
Rayan M. Al-Shehri
Supervising engineer
Hussam T. Al-Qurashi
Project manager
Karim Haddad
Finance & contracts
Khalid N. Al-Mutairi
Authority holder
Munirah A. Al-Khalidi