Saudi Contractors AuthorityMunjaz11My actionsNotifications

Certificate ⁦2⁩ — May 2025

QA & project office support — Muqawil platform

Kingdom of Saudi Arabia

Saudi Contractors Authority

General Directorate of Finance & Procurement — Contracts & Procurement Department

Certificate no.
2
Date
⁦2025-05-31⁩
Hijri
4 Dhuʻl-Hijjah 1446 AH
Reference
PAY-2025-013-02

Interim payment certificate no. (⁦2⁩)

For the work of May 2025

Contract number
SCA/2025/013
Etimad reference
2504020563
Contract
QA & project office support — Muqawil platform
Contractor
Dar Al-Mashura Management Consulting
Contractor VAT number
310106912450003
Project
Muqawil Platform — Release 4
Contract period
⁦2025-03-02⁩ — ⁦2027-05-31⁩
Original contract value
5,400,000
Current contract value
5,400,000
Linked milestone
Mid-term review · MS-05 Internal pilot (MVP) live

Certificate summary (SAR)

1Total value of work completed to date310,000
2Less: previous certificates(120,000)
3Value of work in this certificate190,000
4Less: retention (⁦5%⁩)(9,500)
5Less: advance payment recovery (⁦0%⁩)0
6Less: delay and breach penalties0
7Total deductions(9,500)
8Net before VAT180,500
9Add: value added tax (15%)27,075
10Net amount payable to the contractor207,575

Amount in words: Two hundred seven thousand five hundred seventy-five Saudi riyals only

Retention held up to this certificate: SAR 15.5K — released after final acceptance.

Work by contract item

ItemItem valuePreviousThis periodTo dateComplete
Resident engineering staff3,348,00075,000119,000194,000⁦6%⁩
Visiting specialists972,00022,00034,00056,000⁦6%⁩
Laboratory & testing648,00013,00020,00033,000⁦5%⁩
Reporting & technical office432,00010,00017,00027,000⁦6%⁩
Total5,400,000120,000190,000310,000⁦6%⁩

Amounts in Saudi riyals.

Signatures and approvals

Contractor’s representative

Salma R. Al-Buqami

Al-Buqami⁦2025-05-31⁩

Supervising engineer

Joud N. Al-Ahmadi

Al-Ahmadi⁦2025-06-02⁩

Project manager

Eng. Sultan F. Al-Ghamdi

Al-Ghamdi⁦2025-06-05⁩

Finance & contracts

Khalid N. Al-Mutairi

Al-Mutairi⁦2025-06-08⁩

Authority holder

Munirah A. Al-Khalidi

Al-Khalidi⁦2025-06-11⁩
Issued electronically through Munjaz Integration-ready for Etimad

Approval chain

Fully approved and sent for payment

  1. Certificate submitted⁦2025-05-31⁩

    Salma R. Al-Buqami

  2. Engineer verifies quantities⁦2025-06-02⁩

    Joud N. Al-Ahmadi · QA & Testing Specialist

    Took 2 days

  3. Project manager certifies⁦2025-06-05⁩

    Eng. Sultan F. Al-Ghamdi · Project Manager, Muqawil Platform — Release 4

    Took 3 days

  4. Payment order prepared⁦2025-06-08⁩

    Khalid N. Al-Mutairi · Senior Finance & Procurement SpecialistPayment request creator

    Took 3 days

  5. Final approval⁦2025-06-11⁩

    Munirah A. Al-Khalidi · Director General, Finance & Procurement

    Took 3 days

You are viewing as Dr. Noura M. Al-Otaibi

Linked milestone & deliverables

The certificate is paid against a contract milestone, tied to the project’s milestone and its deliverables

  1. Contract milestoneMid-term reviewDone · ⁦2026-04-16⁩
  2. Project milestoneMS-05Internal pilot (MVP) liveMilestone approved ⁦2026-04-30⁩⁦2⁩ evidence files

Deliverables & completion certificates

No deliverable is tied to this milestone — the evidence is the milestone’s approval and its files.

Segregation of duties

The platform checks these rules on every certificate

  • The payment request’s creator does not approve itKhalid N. Al-Mutairi → Munirah A. Al-Khalidi
  • Whoever verified quantities does not prepare the payment orderJoud N. Al-Ahmadi → Khalid N. Al-Mutairi
  • The project manager does not approve the paymentEng. Sultan F. Al-Ghamdi → Munirah A. Al-Khalidi

Certificate history

11 June 2025

  1. Payment: Munirah A. Al-Khalidi signed “Final approval”

    2025-06-11 13:00

8 June 2025

  1. Approval: Khalid N. Al-Mutairi signed “Payment order prepared”

    2025-06-08 13:00

5 June 2025

  1. Approval: Eng. Sultan F. Al-Ghamdi signed “Project manager certifies”

    2025-06-05 13:00

2 June 2025

  1. Approval: Joud N. Al-Ahmadi signed “Engineer verifies quantities”

    2025-06-02 13:00

31 May 2025

  1. Approval: Contractor signed “Certificate submitted”

    2025-05-31 09:00
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close