SCA/2025/013
Terms, guarantees, milestones, variation orders and payment certificates.
From original to current value
The original value and each approved variation
60% of the current value paid
Paid
3.2Mof a current value of SAR 5.4M
Value of each certificate
The last 13 — gross and net
Approved: 13
Count: 13 · in the approval chain: 0
| Certificate | Submitted | Gross | Retention | Deductions | VAT | Net | Status | |
|---|---|---|---|---|---|---|---|---|
| Certificate 13September 2026 | 2026-10-06 | 120K | 6,000 | 0 | 17.1K | 131.1K | Approved | |
| Certificate 12August 2026 | 2026-08-22 | 180K | 9,000 | 0 | 25.7K | 196.7K | Approved | |
| Certificate 11June 2026 | 2026-07-08 | 210K | 10.5K | 0 | 29.9K | 229.4K | Approved | |
| Certificate 10May 2026 | 2026-05-25 | 300K | 15K | 0 | 42.8K | 327.8K | Approved | |
| Certificate 9March 2026 | 2026-04-10 | 300K | 15K | 0 | 42.8K | 327.8K | Approved | |
| Certificate 8February 2026 | 2026-02-24 | 320K | 16K | 0 | 45.6K | 349.6K | Approved | |
| Certificate 7December 2025 | 2026-01-10 | 380K | 19K | 0 | 54.2K | 415.2K | Approved | |
| Certificate 6November 2025 | 2025-11-26 | 300K | 15K | 0 | 42.8K | 327.8K | Approved | |
| Certificate 5September 2025 | 2025-10-12 | 320K | 16K | 0 | 45.6K | 349.6K | Approved | |
| Certificate 4August 2025 | 2025-08-29 | 290K | 14.5K | 0 | 41.3K | 316.8K | Approved | |
| Certificate 3June 2025 | 2025-07-15 | 210K | 10.5K | 0 | 29.9K | 229.4K | Approved | |
| Certificate 2May 2025 | 2025-05-31 | 190K | 9,500 | 0 | 27.1K | 207.6K | Approved | |
| Certificate 1March 2025 | 2025-04-16 | 120K | 6,000 | 0 | 17.1K | 131.1K | Approved |