Saudi Contractors AuthorityMunjaz11My actionsNotifications

Certificate ⁦3⁩ — February 2026

Muqawil mobile app development

Kingdom of Saudi Arabia

Saudi Contractors Authority

General Directorate of Finance & Procurement — Contracts & Procurement Department

Certificate no.
3
Date
⁦2026-03-01⁩
Hijri
12 Ramadan 1447 AH
Reference
PAY-2025-015-03

Interim payment certificate no. (⁦3⁩)

For the work of February 2026

Contract number
SCA/2025/015
Etimad reference
2504160589
Contract
Muqawil mobile app development
Contractor
Digital Platforms Solutions Co.
Contractor VAT number
310105738640003
Project
Muqawil Mobile App — Release 3
Contract period
⁦2025-10-19⁩ — ⁦2027-01-31⁩
Original contract value
9,800,000
Current contract value
9,800,000
Linked milestone
Release 1 built · MS-G2 Designs approved

Certificate summary (SAR)

1Total value of work completed to date1,970,000
2Less: previous certificates(1,160,000)
3Value of work in this certificate810,000
4Less: retention (⁦5%⁩)(40,500)
5Less: advance payment recovery (⁦0%⁩)0
6Less: delay and breach penalties0
7Total deductions(40,500)
8Net before VAT769,500
9Add: value added tax (15%)115,425
10Net amount payable to the contractor884,925

Amount in words: Eight hundred eighty-four thousand nine hundred twenty-five Saudi riyals only

Retention held up to this certificate: SAR 98.5K — released after final acceptance.

Work by contract item

ItemItem valuePreviousThis periodTo dateComplete
Analysis & design1,470,000266,000168,000434,000⁦30%⁩
Licences & platform1,960,000307,000205,000512,000⁦26%⁩
Build & configuration2,940,000344,000247,000591,000⁦20%⁩
Systems integration1,470,000134,000102,000236,000⁦16%⁩
Testing & acceptance980,00066,00052,000118,000⁦12%⁩
Training & run980,00043,00036,00079,000⁦8%⁩
Total9,800,0001,160,000810,0001,970,000⁦20%⁩

Amounts in Saudi riyals.

Signatures and approvals

Contractor’s representative

Rayan M. Al-Shehri

Al-Shehri⁦2026-03-01⁩

Supervising engineer

Hussam T. Al-Qurashi

Al-Qurashi⁦2026-03-03⁩

Project manager

Karim Haddad

Haddad⁦2026-03-06⁩

Finance & contracts

Khalid N. Al-Mutairi

Al-Mutairi⁦2026-03-09⁩

Authority holder

Munirah A. Al-Khalidi

Al-Khalidi⁦2026-03-12⁩
Issued electronically through Munjaz Integration-ready for Etimad

Approval chain

Fully approved and sent for payment

  1. Certificate submitted⁦2026-03-01⁩

    Rayan M. Al-Shehri

  2. Engineer verifies quantities⁦2026-03-03⁩

    Hussam T. Al-Qurashi · Senior Software Engineer – Integration

    Took 2 days

  3. Project manager certifies⁦2026-03-06⁩

    Karim Haddad · Senior Digital Delivery Consultant — PMO

    Took 3 days

  4. Payment order prepared⁦2026-03-09⁩

    Khalid N. Al-Mutairi · Senior Finance & Procurement SpecialistPayment request creator

    Took 3 days

  5. Final approval⁦2026-03-12⁩

    Munirah A. Al-Khalidi · Director General, Finance & Procurement

    Took 3 days

You are viewing as Dr. Noura M. Al-Otaibi

Linked milestone & deliverables

The certificate is paid against a contract milestone, tied to the project’s milestone and its deliverables

  1. Contract milestoneRelease 1 builtDone · ⁦2026-06-11⁩
  2. Project milestoneMS-G2Designs approvedMilestone approved ⁦2026-07-02⁩1 evidence file

Deliverables & completion certificates

Every linked deliverable is accepted with a completion certificate.

Segregation of duties

The platform checks these rules on every certificate

  • The payment request’s creator does not approve itKhalid N. Al-Mutairi → Munirah A. Al-Khalidi
  • Whoever verified quantities does not prepare the payment orderHussam T. Al-Qurashi → Khalid N. Al-Mutairi
  • The project manager does not approve the paymentKarim Haddad → Munirah A. Al-Khalidi

Certificate history

12 March 2026

  1. Payment: Munirah A. Al-Khalidi signed “Final approval”

    2026-03-12 13:00

9 March 2026

  1. Approval: Khalid N. Al-Mutairi signed “Payment order prepared”

    2026-03-09 13:00

6 March 2026

  1. Approval: Karim Haddad signed “Project manager certifies”

    2026-03-06 13:00

3 March 2026

  1. Approval: Hussam T. Al-Qurashi signed “Engineer verifies quantities”

    2026-03-03 13:00

1 March 2026

  1. Approval: Contractor signed “Certificate submitted”

    2026-03-01 09:00
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close