Interim payment certificate no. (6)
For the work of June 2026
- Contract number
- SCA/2025/015
- Etimad reference
- 2504160589
- Contract
- Muqawil mobile app development
- Contractor
- Digital Platforms Solutions Co.
- Contractor VAT number
- 310105738640003
- Project
- Muqawil Mobile App — Release 3
- Contract period
- 2025-10-19 — 2027-01-31
- Original contract value
- 9,800,000
- Current contract value
- 9,800,000
- Linked milestone
- Integration & UAT · MS-G3 Build complete
Certificate summary (SAR)
| 1 | Total value of work completed to date | 4,930,000 |
| 2 | Less: previous certificates | (4,110,000) |
| 3 | Value of work in this certificate | 820,000 |
| 4 | Less: retention (5%) | (41,000) |
| 5 | Less: advance payment recovery (0%) | 0 |
| 6 | Less: delay and breach penalties | 0 |
| 7 | Total deductions | (41,000) |
| 8 | Net before VAT | 779,000 |
| 9 | Add: value added tax (15%) | 116,850 |
| 10 | Net amount payable to the contractor | 895,850 |
Amount in words: Eight hundred ninety-five thousand eight hundred fifty Saudi riyals only
Retention held up to this certificate: SAR 246.5K — released after final acceptance.
Work by contract item
| Item | Item value | Previous | This period | To date | Complete |
|---|---|---|---|---|---|
| Analysis & design | 1,470,000 | 937,000 | 147,000 | 1,084,000 | 74% |
| Licences & platform | 1,960,000 | 1,088,000 | 194,000 | 1,282,000 | 65% |
| Build & configuration | 2,940,000 | 1,219,000 | 260,000 | 1,479,000 | 50% |
| Systems integration | 1,470,000 | 478,000 | 114,000 | 592,000 | 40% |
| Testing & acceptance | 980,000 | 234,000 | 62,000 | 296,000 | 30% |
| Training & run | 980,000 | 154,000 | 43,000 | 197,000 | 20% |
| Total | 9,800,000 | 4,110,000 | 820,000 | 4,930,000 | 50% |
Amounts in Saudi riyals.
Signatures and approvals
Contractor’s representative
Rayan M. Al-Shehri
Supervising engineer
Hussam T. Al-Qurashi
Project manager
Karim Haddad
Finance & contracts
Khalid N. Al-Mutairi
Authority holder
Munirah A. Al-Khalidi