Project proposal & feasibility study

An electronic form with an auto-filled header, an approval path and its versions, printed with its approval log.

Saudi Contractors AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Proposal

Project proposal & feasibility study

Justification, objectives, benefits, cost and initial risks

Form no.
SCA-PMO-F01
Template edition
2.1
Version
V1
Form date
⁦2026-02-11⁩
Hijri
23 Shaʻban 1447 AH
In approvalDMD-2026-001Smart fault-reporting platform for SCA buildings and centres

Auto-filled — Filled by the platform from the project record, not typed.

Proposal no.
DMD-2026-001
Proposal
Smart fault-reporting platform for SCA buildings and centres
Portfolio
Headquarters & Regional Centres Portfolio
Sector
Corporate Support Sector
Sponsor
Eng. Bandar M. Al-Shammari
Proposed by
Eng. Waleed O. Al-Juhani

1The proposalAuto-filled

TitleAuto-filled
Smart fault-reporting platform for SCA buildings and centres
Proposed byAuto-filled
Eng. Waleed O. Al-Juhani
DepartmentAuto-filled
Facilities Operations & Maintenance Department
Submitted onAuto-filled
⁦2026-02-11⁩
Proposal numberAuto-filled
DMD-2026-001

2Justification

The problem or need

Fault reports from SCA buildings and centres (air-conditioning, e-test hall equipment, lifts, lighting) reach us from branch managers and centre coordinators by phone and email with no single reference number, and about a third get lost between the department and the maintenance contractors.

Today

Average response time is 9.4 days, 31% of reports are closed without a site check, and 46 skills-test sessions were postponed in 2025 because of hall faults.

3Objectives

  1. One reporting platform — a mobile app for branches and centres and a live console — that routes every report to the responsible maintenance team or contractor and brings response time down to 3 days by the end of 2027, and to one day for test-hall faults.

Strategic objectives served

  • SO-1.1 — Simplify regulatory relationships and make doing business easier
  • SO-3.3 — A better contractor experience and service quality

4Expected benefits

KindBenefit
Time savedResponse time down from 9.4 to 3 days
Cost savingSAR 4.2M a year in maintenance savings from early detection
SatisfactionBranch and centre staff satisfaction with facilities up from 61% to 80%

5Cost & feasibilityAuto-filled

Estimated cost

SAR 9.5M

Net present value

SAR 7.2M

Return on investment

⁦74%⁩

Payback

3.0 years

YearCapexOpexBenefit
2027SAR 6.2MSAR 0SAR 0
2028SAR 3.3MSAR 900KSAR 2M
2029SAR 0SAR 950KSAR 4.6M
2030SAR 0SAR 1MSAR 5.8M
2031SAR 0SAR 1MSAR 6.2M
2032SAR 0SAR 1.1MSAR 6.5M

6Initial risks

RiskLevelProposed response
Delay integrating national systemsHighStart integration requests during feasibility
Low user adoption of the new solutionMediumA change plan and champions in each department
Maintenance contractors not closing reports in the systemMediumTie maintenance payments to closed reports

Approval logChain: Proposal & feasibility approval · version ⁦4⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Eng. Waleed O. Al-JuhaniDirector, Facilities Operations & MaintenanceSubmitted—⁦2026-02-11⁩ 12:39
2Line manager endorsementTechnical acceptanceEng. Reem K. Al-DosariThe requester’s line managerApproved—⁦2026-02-15⁩ 14:53
3PMO reviewMethodology reviewGhada A. Al-ShahraniPMO — analystApproved—⁦2026-02-16⁩ 09:00
4Portfolio manager reviewTechnical acceptanceApproval enginePortfolio managerPre-breach alert—⁦2026-10-08⁩ 08:00
5Portfolio manager reviewTechnical acceptanceApproval engineEscalated automatically to PMO — director (Dr. Noura M. Al-Otaibi) on ⁦2026-10-12⁩Automatic escalation—⁦2026-10-12⁩ 08:05

Signatures

Line manager endorsement

Eng. Reem K. Al-Dosari

Approved⁦2026-02-15⁩

PMO review

Ghada A. Al-Shahrani

Approved⁦2026-02-16⁩

Portfolio manager review

Eng. Bandar M. Al-Shammari

Awaiting decision

Cost & funding review

Munirah A. Al-Khalidi

Later

Project Approval Committee

Dr. Noura M. Al-Otaibi

Later

Issued from Munjaz — Saudi Contractors Authority · ⁦2026-10-28⁩Form SCA-PMO-F01 · version V1

Project proposal & feasibility study

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Proposal & feasibility approval · version ⁦4⁩

Submitted by Eng. Waleed O. Al-Juhani on ⁦2026-02-11⁩

  1. Technical acceptance

    Line manager endorsement

    Eng. Reem K. Al-Dosari · The requester’s line manager

    Approved · ⁦2026-02-15⁩ at ⁦14:53⁩

  2. Methodology review

    PMO review

    Ghada A. Al-Shahrani · PMO — analyst

    Approved · ⁦2026-02-16⁩ at ⁦09:00⁩

  3. Technical acceptance

    Portfolio manager review

    Eng. Bandar M. Al-Shammari · Portfolio manager
    14 working days overdueAction time limit exceeded · Limit 3 working daysLimit 3 working days · Due ⁦2026-10-08⁩

    Pre-breach alert at ⁦75%⁩ — sent ⁦2026-10-08⁩

    Escalated automatically to PMO — director (Dr. Noura M. Al-Otaibi) on ⁦2026-10-12⁩

    Waiting on Eng. Bandar M. Al-Shammari
  4. Financial approval

    Cost & funding review

    Munirah A. Al-Khalidi · Finance

    On the path because: Financial link?

    Delegated to Khalid N. Al-Mutairi

    Limit 4 working days · Expected by ⁦2026-10-14⁩

  5. Technical acceptance

    Project Approval Committee

    Dr. Noura M. Al-Otaibi · Project Approval Committee

    Limit 5 working days · Expected by ⁦2026-10-21⁩

Previous versions

Every version is kept with its status and what changed.

  1. V1In approvalCurrent⁦2026-02-11⁩

    First version of the proposal

    • Filled from the proposal wizard

    Eng. Waleed O. Al-Juhani

Only one version so far.