Programme · PG-10 · Institutional Excellence & Governance Portfolio

Institutional Excellence & Capability Programme

On track

The strategy refresh, performance measurement, the Irtiqaa portal and the Academy platform.

Approved budget
SAR 28.4M

incl. SAR 1.5M programme reserve

Actual spend
SAR 14.1M

⁦50%⁩ of budget

EAC
SAR 27M+0.5%

Estimate at completion

Progress
⁦54%⁩

Planned ⁦55%⁩

Schedule performance index
0.98

Cost performance index 1.00

Manager

Ghada A. Al-Shahrani

Director, Qualification Programmes & Capability

Sponsor

Dr. Amal F. Al-Sudairi

Director General, Strategy & Performance

Projects

4 projects

2025-09-07 — 2027-12-31

On track 3At risk 1

Programme objectives

What the programme must achieve, and the strategic objectives it serves.

  1. 1

    Approved execution plans for the SCA strategy, turned into portfolios and initiatives

  2. 2

    Raise PMO maturity to 3.5 out of 5

  3. 3

    25% of relevant SCA staff through specialist development tracks

Programme benefits

From baseline to target

  • PMO maturity index

    by ⁦2027⁩
    Baseline 2.4Current 3.2 of 5Target 3.5
  • Employee engagement index

    by ⁦2027⁩
    Baseline 66Current 71 %Target 75

Roadmap

One lane per project: start to forecast finish, with the progress earned and the baseline finish.

EarnedRemainingBaseline finishSlip
202520262027
2026-12-24
2027-01-31
2026-12-15
2027-12-31

Dependencies between projects

What waits on what. Red links are on the programme’s critical path.

Critical path

What each project needs from the one before

  • The institutional KPI dashboard is built on the new execution plans’ KPIs

  • Change messages start from the approved plan

  • The Academy platform completes the capability programmes and Irtiqaa

Shared risks

Risks that hit more than one project, managed at programme level.

6

A late execution-plan approval delays the new performance KPIs

PRK-10-1·Accept·Abeer H. Al-Shamrani

Affects

Open risks in the programme’s projects

1 risk

Open risks in the programme’s projects
  • Critical0
  • High0
  • Medium1
  • Low0
  • Risks 1
Probability
5
4
3
2
1
12345

Impact

Open risks in the programme’s projects
Probability \ Impact12345
50 · Low0 · Medium0 · High0 · Critical0 · Critical
40 · Low0 · Medium0 · Medium0 · High0 · Critical
30 · Low0 · Low1 · Medium0 · Medium0 · High
20 · Low0 · Low0 · Low0 · Medium0 · Medium
10 · Low0 · Low0 · Low0 · Low0 · Low

Programme KPIs · Stakeholders

Stakeholders

Power against interest; click a person to see their role.

Power

Keep satisfied0

Manage closely4

Monitor0

Keep informed0

Dr. Amal F. Al-SudairiManage closelyDr. Abdullah S. Al-QahtaniManage closelyDr. Noura M. Al-OtaibiManage closelyAbdulmajeed R. Al-DosariManage closely

Interest

Programme decisions

What the committees decided on the programme’s projects, and what the programme raised to them.

Committees

Executive Committee

Weekly · Quorum ⁦4⁩

Dr. Mohammed I. Al-Subaie · Head, Strategy & Institutional Excellence SectorEng. Turki A. Al-Anazi · Head, Qualification & Training SectorEng. Majed S. Al-Rasheed · Head, Digital Transformation SectorSarah A. Al-Qarni · Head, Corporate Support Sector
Chair: Dr. Abdullah S. Al-QahtaniNext meeting 2026-10-28
Project Approval Committee

Fortnightly · Quorum ⁦4⁩

Faisal A. Al-Shehri · Director General, Digital Platforms & Digital Services Portfolio ManagerDr. Amal F. Al-Sudairi · Director General, Strategy & PerformanceTariq S. Al-Yami · Head, Performance & Risk
Chair: Dr. Noura M. Al-OtaibiNext meeting 2026-11-04

Programme projects

The programme’s performance is computed from these projects.

⁦4⁩ results
Export CSV
Manager
Institutional Performance Measurement & KPI DashboardPRJ-2026-012Tariq S. Al-Yami4ExecutionOn track⁦76%⁩9.8M9.8M⁦0.0%⁩1.01Schedule performance index · 1.011.00Cost performance index · 1.00
Irtiqaa Portal — Release 2PRJ-2026-027Ghada A. Al-Shahrani4ExecutionAt risk⁦63%⁩6.4M6.5M⁦+2.0%⁩0.88Schedule performance index · 0.880.98Cost performance index · 0.98
SCA Strategy Refresh & Execution PlansPRJ-2026-028Abeer H. Al-Shamrani4ExecutionOn track⁦70%⁩3.2M3.2M⁦0.0%⁩1.03Schedule performance index · 1.031.00Cost performance index · 1.00
SCA Academy — Learning Platform & Professional TracksPRJ-2026-029Ghada A. Al-Shahrani3PlanningOn track⁦4%⁩7.5M7.5M⁦0.0%⁩1.00Schedule performance index · 1.001.00Cost performance index · 1.00
Total · 426.9M27M
⁦1⁩–⁦4⁩ of ⁦4⁩

Budget shares

Budget shares

SAR 26.9M

Budget

  • Institutional Performance Measurement & KPI DashboardSAR 9.8M⁦36%⁩
  • Irtiqaa Portal — Release 2SAR 6.4M⁦24%⁩
  • SCA Strategy Refresh & Execution PlansSAR 3.2M⁦12%⁩
  • SCA Academy — Learning Platform & Professional TracksSAR 7.5M⁦28%⁩
Budget shares
CategoryValueShare
Institutional Performance Measurement & KPI DashboardSAR 9.8M⁦36%⁩
Irtiqaa Portal — Release 2SAR 6.4M⁦24%⁩
SCA Strategy Refresh & Execution PlansSAR 3.2M⁦12%⁩
SCA Academy — Learning Platform & Professional TracksSAR 7.5M⁦28%⁩
TotalSAR 26.9M⁦100%⁩