RSK-0007Muqawil Platform — Release 4

Membership and service-centre staff resisting the new digital procedures

9MediumIn progress

A risk's detail, response, contingency and residual risk.

Risk statement

From cause to event to impact — with the preventive controls before the event and the contingency after it

Cause

Membership and service-centre staff are used to paper procedures and walk-in reviews, and had little say in designing the services

Preventive controls

  • A change-ambassador network at HQ and in every branch
  • Hands-on training for service-centre staff a month before launch

2 / 2

Event

Membership and service-centre staff resisting the new digital procedures

9MediumTrigger

Under 50% usage in the first month

Contingency

Retire paper requests in steps by a circular from the Secretary-General

Impact

Low adoption and paper requests persisting at the service centres after launch

SAR 300K

Assessment

The level before and after the response

Inherent

5
4
3
2
1
1
2
3
4
5
9Medium

Residual

5
4
3
2
1
1
2
3
4
5
4Low

Exposure

SAR 300K

Residual

⁦56⁩% off the score

Score trend

Last six months

  • Score
  • Target residual

Escalation path

Escalation engine: a high risk unreviewed for 10 days notifies the PM, 15 the programme manager, 20 the PMO director

Last reviewed 13 days ago · Outside the engine — below «high»

  1. Project manager

    Current level

    Eng. Sultan F. Al-Ghamdi

    Currently followed up here
  2. 2

    Programme manager

    Eng. Reem K. Al-Dosari

  3. 3

    PMO director

    Dr. Noura M. Al-Otaibi

  4. 4

    Executive committee

    Dr. Abdullah S. Al-Qahtani

    By the PMO director’s decision

Mitigation plan

Each action with its owner and date — tick it off when complete

⁦0⁩ of ⁦2⁩ done
  • A change-ambassador network at HQ and in every branch

    Nouf M. Al-BalawiNouf M. Al-BalawiChange Management SpecialistP-035n.albalawi@sca.sa
    In progressIn 48 days2026-12-156 Rajab 1448 AH
  • Hands-on training for service-centre staff a month before launch

    Nouf M. Al-BalawiNouf M. Al-BalawiChange Management SpecialistP-035n.albalawi@sca.sa
    Not startedIn 96 days2027-02-0124 Shaʻban 1448 AH

Trigger

Under 50% usage in the first month

Contingency

Retire paper requests in steps by a circular from the Secretary-General

Esc