Hosting and run savings after moving the Authority’s systems to the cloud

At risk

Cost saving · SCA Systems Migration to the Cloud

Baseline

0 SAR M

At go-live, ⁦2026-03-01⁩

Latest reading

1.21 SAR M

6 mo reading

Target after 24 months

7.80 SAR M

On ⁦2028-03-01⁩

Target trajectory vs realised

Monthly readings up to the last measurement, then the forecast if performance keeps its current ratio to plan.

Target trajectory vs realised
  • Realised
  • Target trajectory
  • Forecast
Target trajectory vs realised
PeriodRealisedTarget trajectory
2026-030 SAR M0 SAR M
2026-040.17 SAR M0.20 SAR M
2026-050.42 SAR M0.40 SAR M
2026-060.62 SAR M0.60 SAR M
2026-070.75 SAR M0.90 SAR M
2026-081.14 SAR M1.20 SAR M
2026-091.21 SAR M1.50 SAR M
2026-10 (Forecast)1.47 SAR M1.82 SAR M
2026-11 (Forecast)1.72 SAR M2.13 SAR M
2026-12 (Forecast)1.98 SAR M2.45 SAR M
2027-01 (Forecast)2.23 SAR M2.77 SAR M
2027-02 (Forecast)2.49 SAR M3.08 SAR M
2027-03 (Forecast)2.74 SAR M3.40 SAR M
2027-04 (Forecast)3.04 SAR M3.77 SAR M
2027-05 (Forecast)3.33 SAR M4.13 SAR M
2027-06 (Forecast)3.63 SAR M4.50 SAR M
2027-07 (Forecast)3.93 SAR M4.87 SAR M
2027-08 (Forecast)4.22 SAR M5.23 SAR M
2027-09 (Forecast)4.52 SAR M5.60 SAR M
2027-10 (Forecast)4.81 SAR M5.97 SAR M
2027-11 (Forecast)5.11 SAR M6.33 SAR M
2027-12 (Forecast)5.40 SAR M6.70 SAR M
2028-01 (Forecast)5.70 SAR M7.07 SAR M
2028-02 (Forecast)6 SAR M7.43 SAR M
2028-03 (Forecast)6.29 SAR M7.80 SAR M

Measurement schedule

Counted from go-live on ⁦2026-03-01⁩ · data read Quarterly

  1. 3

    After 3 months

    2026-06-0115 Dhuʻl-Hijjah 1447 AH·Expected 0.60 SAR M·Actual 0.62 SAR M

    to plan⁦103%⁩
  2. 6

    After 6 months

    2026-09-0119 Rabiʻ I 1448 AH·Expected 1.50 SAR M·Actual 1.21 SAR M

    to plan⁦81%⁩
  3. 12

    After 12 months

    2027-03-0122 Ramadan 1448 AH·Expected 3.40 SAR M

    In 124 days2027-03-0122 Ramadan 1448 AH
  4. 24

    After 24 months

    2028-03-015 Shawwal 1449 AH·Expected 7.80 SAR M

    In 490 days2028-03-015 Shawwal 1449 AH

Evidence

5 files backing the readings

  • Measurement data extract — 6 mo

    2026-09-01 · Eng. Nayef H. Al-Buqami · ⁦138⁩ KB

  • Benefit measurement report — 6 mo

    2026-09-01 · Eng. Nayef H. Al-Buqami · ⁦986⁩ KB

  • Measurement data extract — 3 mo

    2026-06-01 · Eng. Nayef H. Al-Buqami · ⁦117⁩ KB

  • Benefit measurement report — 3 mo

    2026-06-01 · Eng. Nayef H. Al-Buqami · ⁦923⁩ KB

  • Approved benefit profile — BEN-027

    2026-01-01 · Eng. Omar H. Bawazir · ⁦412⁩ KB

Corrective actions

What is being done to bring the benefit back to plan

No actions yet — add a plan to bring the benefit back on track.

Activity

1 September 2026

  1. Milestone: Eng. Nayef H. Al-Buqami recorded the ⁦6⁩ mo reading: ⁦1.21⁩ SAR M

    2026-09-01 10:30

1 June 2026

  1. Milestone: Eng. Nayef H. Al-Buqami recorded the ⁦3⁩ mo reading: ⁦0.62⁩ SAR M

    2026-06-01 10:30

1 January 2026

  1. Approval: Eng. Omar H. Bawazir approved the benefit profile and its baseline

    2026-01-01 09:00