Saudi Contractors AuthorityMunjaz11My actionsNotifications

Certificate ⁦10⁩ — November 2024

Design & build — Al-Khobar branch rehabilitation & extension

Kingdom of Saudi Arabia

Saudi Contractors Authority

General Directorate of Finance & Procurement — Contracts & Procurement Department

Certificate no.
10
Date
⁦2024-12-03⁩
Hijri
2 Jumada II 1446 AH
Reference
PAY-2024-003-10

Interim payment certificate no. (⁦10⁩)

For the work of November 2024

Contract number
SCA/2024/003
Etimad reference
2401220043
Contract
Design & build — Al-Khobar branch rehabilitation & extension
Contractor
United Buildings & Operations Co.
Contractor VAT number
320510488360003
Project
Al-Khobar Branch — Rehabilitation & Extension
Contract period
⁦2024-02-01⁩ — ⁦2026-09-30⁩
Original contract value
352,000,000
Current contract value
373,400,000including variations of SAR 21.4M
Linked milestone
Structure complete · MS-G3 Build complete

Certificate summary (SAR)

1Total value of work completed to date72,060,000
2Less: previous certificates(60,760,000)
3Value of work in this certificate11,300,000
4Less: retention (⁦10%⁩)(1,130,000)
5Less: advance payment recovery (⁦10%⁩)(1,130,000)
6Less: delay and breach penalties0
7Total deductions(2,260,000)
8Net before VAT9,040,000
9Add: value added tax (15%)1,356,000
10Net amount payable to the contractor10,396,000

Amount in words: Ten million three hundred ninety-six thousand Saudi riyals only

Retention held up to this certificate: SAR 7.2M — released after final acceptance.

Work by contract item

ItemItem valuePreviousThis periodTo dateComplete
Preliminaries & mobilisation26,138,0009,910,0001,728,00011,638,000⁦45%⁩
Earthworks & foundations67,212,00015,423,0002,736,00018,159,000⁦27%⁩
Concrete & structural works115,754,00020,708,0003,864,00024,572,000⁦21%⁩
Mechanical, electrical & plumbing89,616,00010,096,0002,010,00012,106,000⁦14%⁩
Finishes & external works56,010,0004,030,000834,0004,864,000⁦9%⁩
Testing & commissioning18,670,000593,000128,000721,000⁦4%⁩
Total373,400,00060,760,00011,300,00072,060,000⁦19%⁩

Amounts in Saudi riyals.

Signatures and approvals

Contractor’s representative

Eng. Samer A. Al-Qahtani

Al-Qahtani⁦2024-12-03⁩

Supervising engineer

Eng. Ibrahim A. Al-Ghamdi

Al-Ghamdi⁦2024-12-05⁩

Project manager

Eng. Waleed O. Al-Juhani

Al-Juhani⁦2024-12-08⁩

Finance & contracts

Khalid N. Al-Mutairi

Al-Mutairi⁦2024-12-11⁩

Authority holder

Dr. Abdullah S. Al-Qahtani

Al-Qahtani⁦2024-12-14⁩
Issued electronically through Munjaz Integration-ready for Etimad

Approval chain

Fully approved and sent for payment

  1. Certificate submitted⁦2024-12-03⁩

    Eng. Samer A. Al-Qahtani

  2. Engineer verifies quantities⁦2024-12-05⁩

    Eng. Ibrahim A. Al-Ghamdi · Director, Engineering Supervision

    Took 2 days

  3. Project manager certifies⁦2024-12-08⁩

    Eng. Waleed O. Al-Juhani · Director, Facilities Operations & Maintenance

    Took 3 days

  4. Payment order prepared⁦2024-12-11⁩

    Khalid N. Al-Mutairi · Senior Finance & Procurement SpecialistPayment request creator

    Took 3 days

  5. Final approval⁦2024-12-14⁩

    Dr. Abdullah S. Al-Qahtani · Secretary-General

    Took 3 days

You are viewing as Dr. Noura M. Al-Otaibi

Linked milestone & deliverables

The certificate is paid against a contract milestone, tied to the project’s milestone and its deliverables

  1. Contract milestoneStructure completeDone · ⁦2025-07-20⁩
  2. Project milestoneMS-G3Build completeMilestone approved ⁦2026-07-01⁩1 evidence file

Deliverables & completion certificates

Every linked deliverable is accepted with a completion certificate.

Segregation of duties

The platform checks these rules on every certificate

  • The payment request’s creator does not approve itKhalid N. Al-Mutairi → Dr. Abdullah S. Al-Qahtani
  • Whoever verified quantities does not prepare the payment orderEng. Ibrahim A. Al-Ghamdi → Khalid N. Al-Mutairi
  • The project manager does not approve the paymentEng. Waleed O. Al-Juhani → Dr. Abdullah S. Al-Qahtani

Certificate history

14 December 2024

  1. Payment: Dr. Abdullah S. Al-Qahtani signed “Final approval”

    2024-12-14 13:00

11 December 2024

  1. Approval: Khalid N. Al-Mutairi signed “Payment order prepared”

    2024-12-11 13:00

8 December 2024

  1. Approval: Eng. Waleed O. Al-Juhani signed “Project manager certifies”

    2024-12-08 13:00

5 December 2024

  1. Approval: Eng. Ibrahim A. Al-Ghamdi signed “Engineer verifies quantities”

    2024-12-05 13:00

3 December 2024

  1. Approval: Contractor signed “Certificate submitted”

    2024-12-03 09:00
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close