Kingdom of Saudi Arabia
Saudi Contractors Authority
General Directorate of Finance & Procurement — Contracts & Procurement Department
- Certificate no.
- 32
- Date
- 2026-09-09
- Hijri
- 27 Rabiʻ I 1448 AH
- Reference
- PAY-2026-007
Interim payment certificate no. (32)
For the work of August 2026
- Contract number
- SCA/2024/003
- Etimad reference
- 2401220043
- Contract
- Design & build — Al-Khobar branch rehabilitation & extension
- Contractor
- United Buildings & Operations Co.
- Contractor VAT number
- 320510488360003
- Project
- Al-Khobar Branch — Rehabilitation & Extension
- Contract period
- 2024-02-01 — 2026-09-30
- Original contract value
- 352,000,000
- Current contract value
- 373,400,000including variations of SAR 21.4M
- Linked milestone
- MEP systems installed · MS-G4 Testing & acceptance complete
Certificate summary (SAR)
| 1 | Total value of work completed to date | 268,900,000 |
| 2 | Less: previous certificates | (261,800,000) |
| 3 | Value of work in this certificate | 7,100,000 |
| 4 | Less: retention (10%) | (710,000) |
| 5 | Less: advance payment recovery (10%) | (710,000) |
| 6 | Less: delay and breach penalties | 0 |
| 7 | Total deductions | (1,420,000) |
| 8 | Net before VAT | 5,680,000 |
| 9 | Add: value added tax (15%) | 852,000 |
| 10 | Net amount payable to the contractor | 6,532,000 |
Amount in words: Six million five hundred thirty-two thousand Saudi riyals only
Retention held up to this certificate: SAR 26.9M — released after final acceptance.
Work by contract item
| Item | Item value | Previous | This period | To date | Complete |
|---|---|---|---|---|---|
| Preliminaries & mobilisation | 26,138,000 | 25,696,000 | 442,000 | 26,138,000 | 100% |
| Earthworks & foundations | 67,212,000 | 65,919,000 | 1,293,000 | 67,212,000 | 100% |
| Concrete & structural works | 115,754,000 | 106,659,000 | 2,876,000 | 109,535,000 | 95% |
| Mechanical, electrical & plumbing | 89,616,000 | 43,566,000 | 1,609,000 | 45,175,000 | 50% |
| Finishes & external works | 56,010,000 | 17,398,000 | 753,000 | 18,151,000 | 32% |
| Testing & commissioning | 18,670,000 | 2,562,000 | 127,000 | 2,689,000 | 14% |
| Total | 373,400,000 | 261,800,000 | 7,100,000 | 268,900,000 | 72% |
Amounts in Saudi riyals.
Signatures and approvals
Contractor’s representative
Eng. Samer A. Al-Qahtani
Supervising engineer
Eng. Ibrahim A. Al-Ghamdi
Project manager
Eng. Waleed O. Al-Juhani
Finance & contracts
Khalid N. Al-Mutairi
Authority holder
Dr. Abdullah S. Al-Qahtani