AI insight
An escalated contract needs a decision
Open claims: 3; pending variations worth SAR 3.8M. A settlement session with the contractor is advised before deciding the next certificate.
Confidence84%
SCA/2024/003
Terms, guarantees, milestones, variation orders and payment certificates.
From original to current value
Variations pending: 1 worth SAR 3.8M — if approved the value becomes SAR 377.2M
72% of the current value paid
Paid
268.9Mof a current value of SAR 373.4M
AI insight
Open claims: 3; pending variations worth SAR 3.8M. A settlement session with the contractor is advised before deciding the next certificate.
Value of each certificate
The last 14 — gross and net
Approved: 32
Count: 33 · in the approval chain: 1
| Certificate | Submitted | Gross | Retention | Deductions | VAT | Net | Status | |
|---|---|---|---|---|---|---|---|---|
| Certificate 33September 2026 | 2026-10-08 | 5.4M | 540K | 920K | 591K | 4.5M | Returned | |
| Certificate 32August 2026 | 2026-09-09 | 7.1M | 710K | 710K | 852K | 6.5M | Approved | |
| Certificate 31July 2026 | 2026-08-06 | 6.2M | 620K | 620K | 744K | 5.7M | Approved | |
| Certificate 30June 2026 | 2026-07-05 | 3.4M | 344K | 344K | 412.8K | 3.2M | Approved | |
| Certificate 29May 2026 | 2026-06-06 | 4.6M | 457K | 457K | 548.4K | 4.2M | Approved | |
| Certificate 28April 2026 | 2026-05-08 | 5M | 503K | 503K | 603.6K | 4.6M | Approved | |
| Certificate 27March 2026 | 2026-04-09 | 6.1M | 606K | 606K | 727.2K | 5.6M | Approved | |
| Certificate 26February 2026 | 2026-03-11 | 7.4M | 742K | 742K | 890.4K | 6.8M | Approved | |
| Certificate 25January 2026 | 2026-02-10 | 7M | 703K | 703K | 843.6K | 6.5M | Approved | |
| Certificate 24December 2025 | 2026-01-12 | 8.9M | 885K | 885K | 1.1M | 8.1M | Approved | |
| Certificate 23November 2025 | 2025-12-14 | 9.4M | 943K | 943K | 1.1M | 8.7M | Approved | |
| Certificate 22October 2025 | 2025-11-15 | 8.8M | 880K | 880K | 1.1M | 8.1M | Approved | |
| Certificate 21September 2025 | 2025-10-17 | 11.2M | 1.1M | 1.1M | 1.3M | 10.3M | Approved | |
| Certificate 20August 2025 | 2025-09-18 | 10.4M | 1M | 1M | 1.2M | 9.6M | Approved | |
| Certificate 19July 2025 | 2025-08-20 | 10.4M | 1M | 1M | 1.3M | 9.6M | Approved | |
| Certificate 18July 2025 | 2025-07-22 | 12.6M | 1.3M | 1.3M | 1.5M | 11.6M | Approved | |
| Certificate 17June 2025 | 2025-06-23 | 10.6M | 1.1M | 1.1M | 1.3M | 9.7M | Approved | |
| Certificate 16May 2025 | 2025-05-25 | 11.7M | 1.2M | 1.2M | 1.4M | 10.8M | Approved | |
| Certificate 15April 2025 | 2025-04-27 | 12.6M | 1.3M | 1.3M | 1.5M | 11.5M | Approved | |
| Certificate 14March 2025 | 2025-03-29 | 10.3M | 1M | 1M | 1.2M | 9.4M | Approved | |
| Certificate 13February 2025 | 2025-02-28 | 12.1M | 1.2M | 1.2M | 1.5M | 11.2M | Approved | |
| Certificate 12January 2025 | 2025-01-30 | 11.3M | 1.1M | 1.1M | 1.4M | 10.4M | Approved | |
| Certificate 11December 2024 | 2025-01-01 | 9.7M | 974K | 974K | 1.2M | 9M | Approved | |
| Certificate 10November 2024 | 2024-12-03 | 11.3M | 1.1M | 1.1M | 1.4M | 10.4M | Approved | |
| Certificate 9October 2024 | 2024-11-04 | 9.3M | 929K | 929K | 1.1M | 8.5M | Approved | |
| Certificate 8September 2024 | 2024-10-06 | 8.8M | 878K | 878K | 1.1M | 8.1M | Approved | |
| Certificate 7August 2024 | 2024-09-07 | 9.2M | 922K | 922K | 1.1M | 8.5M | Approved | |
| Certificate 6July 2024 | 2024-08-09 | 7.1M | 711K | 711K | 853.2K | 6.5M | Approved | |
| Certificate 5June 2024 | 2024-07-11 | 7.1M | 707K | 707K | 848.4K | 6.5M | Approved | |
| Certificate 4May 2024 | 2024-06-12 | 6.4M | 638K | 638K | 765.6K | 5.9M | Approved | |
| Certificate 3April 2024 | 2024-05-14 | 4.9M | 492K | 492K | 590.4K | 4.5M | Approved | |
| Certificate 2March 2024 | 2024-04-15 | 4.5M | 452K | 452K | 542.4K | 4.2M | Approved | |
| Certificate 1February 2024 | 2024-03-17 | 3.5M | 347K | 347K | 416.4K | 3.2M | Approved |