Saudi Contractors AuthorityMunjaz11My actionsNotifications

Certificate ⁦7⁩ — August 2024

Design & build — Al-Khobar branch rehabilitation & extension

Kingdom of Saudi Arabia

Saudi Contractors Authority

General Directorate of Finance & Procurement — Contracts & Procurement Department

Certificate no.
7
Date
⁦2024-09-07⁩
Hijri
4 Rabiʻ I 1446 AH
Reference
PAY-2024-003-07

Interim payment certificate no. (⁦7⁩)

For the work of August 2024

Contract number
SCA/2024/003
Etimad reference
2401220043
Contract
Design & build — Al-Khobar branch rehabilitation & extension
Contractor
United Buildings & Operations Co.
Contractor VAT number
320510488360003
Project
Al-Khobar Branch — Rehabilitation & Extension
Contract period
⁦2024-02-01⁩ — ⁦2026-09-30⁩
Original contract value
352,000,000
Current contract value
373,400,000including variations of SAR 21.4M
Linked milestone
Earthworks & foundations complete · MS-G2 Designs approved

Certificate summary (SAR)

1Total value of work completed to date42,690,000
2Less: previous certificates(33,470,000)
3Value of work in this certificate9,220,000
4Less: retention (⁦10%⁩)(922,000)
5Less: advance payment recovery (⁦10%⁩)(922,000)
6Less: delay and breach penalties0
7Total deductions(1,844,000)
8Net before VAT7,376,000
9Add: value added tax (15%)1,106,400
10Net amount payable to the contractor8,482,400

Amount in words: Eight million four hundred eighty-two thousand four hundred Saudi riyals only

Retention held up to this certificate: SAR 4.3M — released after final acceptance.

Work by contract item

ItemItem valuePreviousThis periodTo dateComplete
Preliminaries & mobilisation26,138,0005,449,0001,445,0006,894,000⁦26%⁩
Earthworks & foundations67,212,0008,485,0002,273,00010,758,000⁦16%⁩
Concrete & structural works115,754,00011,408,0003,149,00014,557,000⁦13%⁩
Mechanical, electrical & plumbing89,616,0005,572,0001,600,0007,172,000⁦8%⁩
Finishes & external works56,010,0002,227,000655,0002,882,000⁦5%⁩
Testing & commissioning18,670,000329,00098,000427,000⁦2%⁩
Total373,400,00033,470,0009,220,00042,690,000⁦11%⁩

Amounts in Saudi riyals.

Signatures and approvals

Contractor’s representative

Eng. Samer A. Al-Qahtani

Al-Qahtani⁦2024-09-07⁩

Supervising engineer

Eng. Ibrahim A. Al-Ghamdi

Al-Ghamdi⁦2024-09-09⁩

Project manager

Eng. Waleed O. Al-Juhani

Al-Juhani⁦2024-09-12⁩

Finance & contracts

Khalid N. Al-Mutairi

Al-Mutairi⁦2024-09-15⁩

Authority holder

Dr. Abdullah S. Al-Qahtani

Al-Qahtani⁦2024-09-18⁩
Issued electronically through Munjaz Integration-ready for Etimad

Approval chain

Fully approved and sent for payment

  1. Certificate submitted⁦2024-09-07⁩

    Eng. Samer A. Al-Qahtani

  2. Engineer verifies quantities⁦2024-09-09⁩

    Eng. Ibrahim A. Al-Ghamdi · Director, Engineering Supervision

    Took 2 days

  3. Project manager certifies⁦2024-09-12⁩

    Eng. Waleed O. Al-Juhani · Director, Facilities Operations & Maintenance

    Took 3 days

  4. Payment order prepared⁦2024-09-15⁩

    Khalid N. Al-Mutairi · Senior Finance & Procurement SpecialistPayment request creator

    Took 3 days

  5. Final approval⁦2024-09-18⁩

    Dr. Abdullah S. Al-Qahtani · Secretary-General

    Took 3 days

You are viewing as Dr. Noura M. Al-Otaibi

Linked milestone & deliverables

The certificate is paid against a contract milestone, tied to the project’s milestone and its deliverables

  1. Contract milestoneEarthworks & foundations completeDone · ⁦2024-10-30⁩
  2. Project milestoneMS-G2Designs approvedMilestone approved ⁦2025-07-11⁩1 evidence file

Deliverables & completion certificates

Every linked deliverable is accepted with a completion certificate.

Segregation of duties

The platform checks these rules on every certificate

  • The payment request’s creator does not approve itKhalid N. Al-Mutairi → Dr. Abdullah S. Al-Qahtani
  • Whoever verified quantities does not prepare the payment orderEng. Ibrahim A. Al-Ghamdi → Khalid N. Al-Mutairi
  • The project manager does not approve the paymentEng. Waleed O. Al-Juhani → Dr. Abdullah S. Al-Qahtani

Certificate history

18 September 2024

  1. Payment: Dr. Abdullah S. Al-Qahtani signed “Final approval”

    2024-09-18 13:00

15 September 2024

  1. Approval: Khalid N. Al-Mutairi signed “Payment order prepared”

    2024-09-15 13:00

12 September 2024

  1. Approval: Eng. Waleed O. Al-Juhani signed “Project manager certifies”

    2024-09-12 13:00

9 September 2024

  1. Approval: Eng. Ibrahim A. Al-Ghamdi signed “Engineer verifies quantities”

    2024-09-09 13:00

7 September 2024

  1. Approval: Contractor signed “Certificate submitted”

    2024-09-07 09:00
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close